Permit Application Status

PRMH202416563


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202416563
Mechanical/HVAC
Finaled
700 AMERICAN LLLP
Alteration/Repair/Replace
Complete HVAC system for new 128 unit apartment
12/23/2024
01/13/2025
06/14/2026
12/16/2025

Locations

Permits

Permit Number: PRMH202416563

Mechanical
Finaled
01/13/2025
06/14/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Rough-in Inspection Partial Pass 6/27/2025 (8:00 - 10:00) 6/27/2025 (AM) 06/27/2025
Corrections:


Miscellaneous/Other
Carried Forward
06/30/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.

Mechanical Rough-in Inspection Partial Pass 6/30/2025 (10:00 - 12:00) 6/30/2025 (PM) 06/30/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/03/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.

Miscellaneous/Other
Carried Forward
07/03/2025
6/30- 503 duct RI pass-ready for soffit. 30 PSI gas pressure test for rooftop units garage to roof.

Mechanical Rough-in Inspection Partial Pass 7/3/2025 (10:00 - 12:00) 7/3/2025 (AM) 07/03/2025
Corrections:


Miscellaneous/Other
Outstanding
07/03/2025
7/3- 4th floor partial pass except,ready for insulation/vapor barrier/sheetrock.

Mechanical Rough-in Inspection Partial Pass 7/11/2025 (10:00 - 12:00) 7/11/2025 (AM) 07/11/2025
Corrections:


Miscellaneous/Other
Outstanding
07/11/2025
7/11-West 3rd floor rough in partial pass-Room 318 gas line nail plate correction needed.

Mechanical Rough-in Inspection Partial Pass 7/9/2025 (10:00 - 12:00) 7/9/2025 (AM) 07/14/2025
Corrections:


Miscellaneous/Other
Outstanding
07/03/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.

Miscellaneous/Other
Outstanding
07/03/2025
6/30- 503 duct RI pass-ready for soffit. 30 PSI gas pressure test for rooftop units garage to roof.

Miscellaneous/Other
Outstanding
07/14/2025
7/9- 5th floor duct work inspection for soffits.

Mechanical Rough-in Inspection Partial Pass 7/14/2025 (8:00 - 10:00) 7/14/2025 (AM) 07/14/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/14/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.

Miscellaneous/Other
Carried Forward
07/14/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.

Mechanical Rough-in Inspection Partial Pass 7/16/2025 (10:00 - 12:00) 7/16/2025 (AM) 07/17/2025
Corrections:


Miscellaneous/Other
Carried Forward
07/17/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.

Miscellaneous/Other
Carried Forward
07/17/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.

Miscellaneous/Other
Carried Forward
07/17/2025
7/16- 5th floor soffit inspection

Mechanical Rough-in Inspection Partial Pass 7/21/2025 (8:00 - 10:00) 7/21/2025 (AM) 08/08/2025
Corrections:


Miscellaneous/Other
Outstanding
07/17/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.

Miscellaneous/Other
Outstanding
07/17/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.

Miscellaneous/Other
Outstanding
07/17/2025
7/16- 5th floor soffit inspection

Miscellaneous/Other
Outstanding
08/08/2025
7/21-5th floor soffit pass

Mechanical Rough-in Inspection Partial Pass 7/22/2025 (8:00 - 10:00) 7/22/2025 (AM) 08/08/2025
Mechanical Rough-in Inspection Partial Pass 7/24/2025 (12:30 - 2:30) 7/24/2025 (PM) 08/08/2025
Mechanical Rough-in Inspection Partial Pass 7/25/2025 (8:00 - 10:00) 7/25/2025 (AM) 08/08/2025
Corrections:


Miscellaneous/Other
Outstanding
08/08/2025
2nd floor west 1st inspection

Mechanical Rough-in Inspection Partial Pass 7/29/2025 (2:30 - 3:30) 7/29/2025 (PM) 08/08/2025
Corrections:


Miscellaneous/Other
Outstanding
08/08/2025
4th floor walk through

Mechanical Rough-in Inspection Partial Pass 8/1/2025 (10:00 - 12:00) 8/1/2025 (AM) 08/08/2025
2nd floor(East half of floor)
Corrections:


Miscellaneous/Other
Outstanding
08/08/2025
2nd floor east 1st rough in

Mechanical Rough-in Inspection Partial Pass 8/6/2025 (8:00 - 10:00) 8/6/2025 (AM) 08/08/2025
Corrections:


Miscellaneous/Other
Outstanding
08/08/2025
8/6-3rd floor west end soffits

Mechanical Rough-in Inspection Partial Pass 8/8/2025 (8:00 - 10:00) 8/8/2025 (AM) 08/08/2025
Corrections:


Miscellaneous/Other
Carried Forward
08/08/2025
1st floor west 1st inspection-some problems

Progress Inspection Passed 08/12/2025
Corrections:


Miscellaneous/Other
Comment Only
08/12/2025
Combustion air intake and ducting at soffits of 3rd floor area A units... approved

Mechanical Rough-in Inspection Passed 8/13/2025 (12:30 - 2:30) 8/13/2025 (PM) 08/13/2025
Corrections:


Miscellaneous/Other
Resolved
08/13/2025
1st floor west 1st inspection-some problems

Miscellaneous/Other
Comment Only
08/13/2025
Remaining units of 3rd floor area A, combustion air and supply ducting at soffits... approved This completes the ducting rough in for 3rd floor.

Mechanical Rough-in Inspection Passed 8/20/2025 (10:00 - 12:00) 8/20/2025 (AM) 08/20/2025
Corrections:


Miscellaneous/Other
Comment Only
08/20/2025
First floor area A rough in of dryer venting, bath fan venting, and gas lines and fresh air intake. Second floor area B unit ducting and fresh iar intake at soffits. Approved.

Mechanical Rough-in Inspection Passed 8/27/2025 (8:00 - 10:00) 8/27/2025 (AM) 08/27/2025
Corrections:


Miscellaneous/Other
Comment Only
08/27/2025
Gas line air tests for oaa units gas piping holding at 30psi... approved Unit ducting at soffits of 2nd floor area A. Ducting with insulation wrap and installed hvac units in commons area.

Progress Inspection Passed 09/03/2025
Corrections:


Miscellaneous/Other
Comment Only
09/03/2025
Unit supply and fresh air intake ducting at soffits in units of first floor area A... approved

Progress Inspection Passed 09/11/2025
Corrections:


Miscellaneous/Other
Comment Only
09/11/2025
Remainder of soffit ducting and hallway ducting of first floor... approved

Mechanical Rough-in Inspection Passed 9/12/2025 (12:30 - 2:30) 9/12/2025 (PM) 09/12/2025
Corrections:


Miscellaneous/Other
Comment Only
09/12/2025
Ducting and dampers in mechanical shafts areas A&B , floors 3,4,&5... approved

Mechanical Rough-in Inspection Passed 10/14/2025 (12:30 - 2:30) 10/14/2025 (PM) 10/14/2025
Corrections:


Miscellaneous/Other
Comment Only
10/14/2025
Air test holding at 30psi for the gas main piping... approved

Mechanical Rough-in Inspection Passed 10/16/2025 (8:00 - 10:00) 10/16/2025 (AM) 10/16/2025
Corrections:


Miscellaneous/Other
Comment Only
10/16/2025
Piping connection from generator to meter... approved Buriel depth of gas piping of min. 18" in depth... approved

Mechanical Final Inspection Passed 10/30/2025 (8:00 - 10:00) 10/30/2025 (AM) 10/30/2025
Corrections:


Miscellaneous/Other
Comment Only
10/30/2025
Fourth and fifthe floor units mechanical... mechanical final for the units approved

Mechanical Final Inspection Partial Pass 11/6/2025 (8:00 - 10:00) 11/6/2025 (AM) 11/06/2025
Corrections:


Miscellaneous/Other
Comment Only
11/06/2025
final for all mechanicals in units of 2nd and 3rd floor... approved

Mechanical Final Inspection Partial Pass 11/17/2025 (8:00 - 10:00) 11/17/2025 (AM) 11/17/2025
Corrections:


Miscellaneous/Other
Comment Only
11/17/2025
Mechanical final in all units from fifth floor down to first floor and including first floor... approved

Mechanical Final Inspection Partial Pass 12/8/2025 (8:00 - 10:00) 12/8/2025 (AM) 12/08/2025
Corrections:


Miscellaneous/Other
Comment Only
12/08/2025
Progress inspection for upcoming final... viewed roof equipment, installs approved. First floor mechanical in units and common areas approved. Set up inspection for garage CO testing and all damper tests.

Mechanical Final Inspection Partial Pass 12/15/2025
Corrections:


Miscellaneous/Other
Comment Only
12/15/2025
Dampers testing of building has been tested and approved. CO 2 testing in garage has been tested and approved.

Mechanical Final Inspection Passed 12/16/2025
Corrections:


Miscellaneous/Other
Comment Only
12/16/2025
N/O system tesing completed and approved. All required testing is completed and work associated with this permit is completed. Final approved