PRMH202416563
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 6/27/2025 (8:00 - 10:00) | 6/27/2025 (AM) | 06/27/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/30/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/30/2025 (10:00 - 12:00) | 6/30/2025 (PM) | 06/30/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/03/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.
|
||||
|
Miscellaneous/Other
Carried Forward
07/03/2025
6/30- 503 duct RI pass-ready for soffit. 30 PSI gas pressure test for rooftop units garage to roof.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/3/2025 (10:00 - 12:00) | 7/3/2025 (AM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/03/2025
7/3- 4th floor partial pass except,ready for insulation/vapor barrier/sheetrock.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/11/2025 (10:00 - 12:00) | 7/11/2025 (AM) | 07/11/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/11/2025
7/11-West 3rd floor rough in partial pass-Room 318 gas line nail plate correction needed.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/9/2025 (10:00 - 12:00) | 7/9/2025 (AM) | 07/14/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/03/2025
6/27- 501,502 and 503 pass rough in and 1/2 of 4 th floor pass rough in.
|
||||
|
Miscellaneous/Other
Outstanding
07/03/2025
6/30- 503 duct RI pass-ready for soffit. 30 PSI gas pressure test for rooftop units garage to roof.
|
||||
|
Miscellaneous/Other
Outstanding
07/14/2025
7/9- 5th floor duct work inspection for soffits.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/14/2025 (8:00 - 10:00) | 7/14/2025 (AM) | 07/14/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/14/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.
|
||||
|
Miscellaneous/Other
Carried Forward
07/14/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/16/2025 (10:00 - 12:00) | 7/16/2025 (AM) | 07/17/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/17/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.
|
||||
|
Miscellaneous/Other
Carried Forward
07/17/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.
|
||||
|
Miscellaneous/Other
Carried Forward
07/17/2025
7/16- 5th floor soffit inspection
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/21/2025 (8:00 - 10:00) | 7/21/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
07/17/2025
7/11- 3rd floor rough in partial pass. Room318 missed nail plate.
|
||||
|
Miscellaneous/Other
Outstanding
07/17/2025
7/14- Gas lines 30 psi test pass on group 27,26,25,23,22,21,20 and 16.
|
||||
|
Miscellaneous/Other
Outstanding
07/17/2025
7/16- 5th floor soffit inspection
|
||||
|
Miscellaneous/Other
Outstanding
08/08/2025
7/21-5th floor soffit pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 08/08/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 7/24/2025 (12:30 - 2:30) | 7/24/2025 (PM) | 08/08/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 7/25/2025 (8:00 - 10:00) | 7/25/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
2nd floor west 1st inspection
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/29/2025 (2:30 - 3:30) | 7/29/2025 (PM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
4th floor walk through
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/1/2025 (10:00 - 12:00) | 8/1/2025 (AM) | 08/08/2025 |
| 2nd floor(East half of floor) | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
2nd floor east 1st rough in
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/6/2025 (8:00 - 10:00) | 8/6/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/08/2025
8/6-3rd floor west end soffits
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 8/8/2025 (8:00 - 10:00) | 8/8/2025 (AM) | 08/08/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/08/2025
1st floor west 1st inspection-some problems
|
||||
| Progress Inspection | Passed | 08/12/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/12/2025
Combustion air intake and ducting at soffits of 3rd floor area A units... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 8/13/2025 (12:30 - 2:30) | 8/13/2025 (PM) | 08/13/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/13/2025
1st floor west 1st inspection-some problems
|
||||
|
Miscellaneous/Other
Comment Only
08/13/2025
Remaining units of 3rd floor area A, combustion air and supply ducting at soffits... approved
This completes the ducting rough in for 3rd floor.
|
||||
| Mechanical Rough-in Inspection | Passed | 8/20/2025 (10:00 - 12:00) | 8/20/2025 (AM) | 08/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/20/2025
First floor area A rough in of dryer venting, bath fan venting, and gas lines and fresh air intake.
Second floor area B unit ducting and fresh iar intake at soffits.
Approved.
|
||||
| Mechanical Rough-in Inspection | Passed | 8/27/2025 (8:00 - 10:00) | 8/27/2025 (AM) | 08/27/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/27/2025
Gas line air tests for oaa units gas piping holding at 30psi... approved
Unit ducting at soffits of 2nd floor area A.
Ducting with insulation wrap and installed hvac units in commons area.
|
||||
| Progress Inspection | Passed | 09/03/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2025
Unit supply and fresh air intake ducting at soffits in units of first floor area A... approved
|
||||
| Progress Inspection | Passed | 09/11/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
09/11/2025
Remainder of soffit ducting and hallway ducting of first floor... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 9/12/2025 (12:30 - 2:30) | 9/12/2025 (PM) | 09/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/12/2025
Ducting and dampers in mechanical shafts areas A&B , floors 3,4,&5... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 10/14/2025 (12:30 - 2:30) | 10/14/2025 (PM) | 10/14/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/14/2025
Air test holding at 30psi for the gas main piping... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 10/16/2025 (8:00 - 10:00) | 10/16/2025 (AM) | 10/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/16/2025
Piping connection from generator to meter... approved
Buriel depth of gas piping of min. 18" in depth... approved
|
||||
| Mechanical Final Inspection | Passed | 10/30/2025 (8:00 - 10:00) | 10/30/2025 (AM) | 10/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
Fourth and fifthe floor units mechanical... mechanical final for the units approved
|
||||
| Mechanical Final Inspection | Partial Pass | 11/6/2025 (8:00 - 10:00) | 11/6/2025 (AM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
final for all mechanicals in units of 2nd and 3rd floor... approved
|
||||
| Mechanical Final Inspection | Partial Pass | 11/17/2025 (8:00 - 10:00) | 11/17/2025 (AM) | 11/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/17/2025
Mechanical final in all units from fifth floor down to first floor and including first floor... approved
|
||||
| Mechanical Final Inspection | Partial Pass | 12/8/2025 (8:00 - 10:00) | 12/8/2025 (AM) | 12/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/08/2025
Progress inspection for upcoming final... viewed roof equipment, installs approved. First floor mechanical in units and common areas approved.
Set up inspection for garage CO testing and all damper tests.
|
||||
| Mechanical Final Inspection | Partial Pass | 12/15/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/15/2025
Dampers testing of building has been tested and approved.
CO 2 testing in garage has been tested and approved.
|
||||
| Mechanical Final Inspection | Passed | 12/16/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/16/2025
N/O system tesing completed and approved.
All required testing is completed and work associated with this permit is completed. Final approved
|
||||