PRMH202416565
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Pending | |||
|
Corrections:
Miscellaneous/Other
Outstanding
06/24/2025
6/24-5th floor RI partial pass ready for insulation/sheetrock except for room 501,502 and 504.
|
||||
| Mechanical Rough-in Inspection | Not Ready | 1/13/2025 (10:00 - 12:00) | 1/13/2025 (AM) | 01/13/2025 |
| Mechanical Final Inspection | Not Ready | 1/13/2025 (10:00 - 12:00) | 1/13/2025 (AM) | 01/13/2025 |
| Mechanical Rough-in Inspection | Partial Pass | 6/24/2025 (8:00 - 10:00) | 6/24/2025 (AM) | 06/24/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/24/2025
6/24-5th floor RI partial pass ready for insulation/sheetrock except for room 501,502 and 504.
|
||||
| Mechanical Final Inspection | Closed | 12/15/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
12/15/2025
Temp heat has been removed.
|
||||