PRMH202416607
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 3/18/2025 (12:30 - 2:30) | 3/18/2025 (PM) | 03/18/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
03/18/2025
3/18- 30 PSI air test on gas piping passed.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 4/3/2025 (12:30 - 2:30) | 4/3/2025 (PM) | 04/03/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/03/2025
3/18- 30 PSI air test on gas piping passed.
|
||||
|
Miscellaneous/Other
Carried Forward
04/03/2025
4/3- exhaust and supply duct inspection above hard life ceiling on south of building
|
||||
| Mechanical Rough-in Inspection | Passed | 9/17/2025 (8:00 - 10:00) | 9/17/2025 (AM) | 09/17/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
09/17/2025
3/18- 30 PSI air test on gas piping passed.
|
||||
|
Miscellaneous/Other
Resolved
09/17/2025
4/3- exhaust and supply duct inspection above hard life ceiling on south of building
|
||||
|
Miscellaneous/Other
Comment Only
09/17/2025
All ducting rough in approved and ok to insulate.
Light test to grease ducts... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 10/22/2025 (8:00 - 10:00) | 10/22/2025 (AM) | 10/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/22/2025
Gas meter hookup... approved
Air test on all gas lines holding at 30 psi... approved
|
||||
| Mechanical Final Inspection | Passed | 10/24/2025 (8:00 - 10:00) | 10/24/2025 (AM) | 10/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/24/2025
Mechanical Rough in for all ducting,and exhaust fans... approved
|
||||
| Mechanical Final Inspection | Not Ready | 10/24/2025 | ||
|
Corrections:
Miscellaneous/Other
Carried Forward
10/24/2025
Testing of hoods needed, schedule capture test for final inspection.
|
||||
| Mechanical Final Inspection | Passed | 11/24/2025 (10:00 - 12:00) | 11/24/2025 (AM) | 11/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/24/2025
Capture test to hood at fryers and ovens... approved.
Final for this permit approved
|
||||