Permit Application Status

PRMH202416716


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRMH202416716
Mechanical/HVAC
Permit(s) Issued
;
SEAGATE TECHNOLOGY INC
Alteration/Repair/Replace
Installing condensate, chilled water, hot water, natural gas, steam, house vac, process cooling, DI water, process vac, compressed air, nitrogen gas, and chemical waste piping. Installing condensing boilers, centrifugal chillers, turbo disc, hydronic pumps, heat exchanger, air control, fan coil units, hydronic heaters, humidifiers, scrubber tank, chemical treatment system,house vac system, process chilled system, CA system, process vac & DI water system.
12/31/2024
03/10/2025
05/18/2026

Locations

Permits

Permit Number: PRMH202416716

Mechanical
Issued
03/10/2025
05/18/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Mechanical Final Inspection Pending
Mechanical Rough-in Inspection Pending 12/17/2025 (12:30 - 2:30) 12/17/2025 (PM)
Progress Inspection Partial Pass 4/23/2025 (8:00 - 10:00) 4/23/2025 (AM) 04/23/2025
Corrections:


Miscellaneous/Other
Carried Forward
04/23/2025
4/23- Walk through entire building project with fitter and tinner foreman.

Mechanical Rough-in Inspection Partial Pass 9/2/2025 (2:30 - 3:30) 9/2/2025 (PM) 09/02/2025
Corrections:


Miscellaneous/Other
Comment Only
09/02/2025
Visual inspection and air test for 3" gas main that enters on Northeast side of the building okay.

Mechanical Rough-in Inspection Not Ready 9/3/2025 (2:30 - 3:30) 9/3/2025 (PM) 09/03/2025
Corrections:


Miscellaneous/Other
Comment Only
09/03/2025
Contractor to reschedule hydro test when they receive another high pressure hose.

Mechanical Final Inspection Partial Pass 9/25/2025 (10:00 - 12:00) 9/25/2025 (AM) 09/25/2025
Corrections:


Miscellaneous/Other
Comment Only
09/25/2025
Hydrostatic test on supply heating water (HWS per plan) piping okay.

Mechanical Rough-in Inspection Partial Pass 11/19/2025 (8:00 - 10:00) 11/19/2025 (AM) 11/19/2025
Corrections:


Miscellaneous/Other
Comment Only
11/19/2025
Visual inspection of rough ducting and labeling okay. As discussed, schedule another inspection when when more progress is made and when specific areas are full completed.