PRMH202416716
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Final Inspection | Pending | |||
| Progress Inspection | Partial Pass | 4/23/2025 (8:00 - 10:00) | 4/23/2025 (AM) | 04/23/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
04/23/2025
4/23- Walk through entire building project with fitter and tinner foreman.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 9/2/2025 (2:30 - 3:30) | 9/2/2025 (PM) | 09/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2025
Visual inspection and air test for 3" gas main that enters on Northeast side of the building okay.
|
||||
| Mechanical Rough-in Inspection | Not Ready | 9/3/2025 (2:30 - 3:30) | 9/3/2025 (PM) | 09/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2025
Contractor to reschedule hydro test when they receive another high pressure hose.
|
||||
| Mechanical Final Inspection | Partial Pass | 9/25/2025 (10:00 - 12:00) | 9/25/2025 (AM) | 09/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/25/2025
Hydrostatic test on supply heating water (HWS per plan) piping okay.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 11/19/2025 (8:00 - 10:00) | 11/19/2025 (AM) | 11/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/19/2025
Visual inspection of rough ducting and labeling okay. As discussed, schedule another inspection when when more progress is made and when specific areas are full completed.
|
||||
| Mechanical Rough-in Inspection | Passed | 12/17/2025 (12:30 - 2:30) | 12/17/2025 (PM) | 12/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/17/2025
Boiler testing with the state of Mn. The state boiler inspector did all the testing of the two boiler units, boilers passed state inspection.
|
||||
| Mechanical Final Inspection | Partial Pass | 2/11/2026 | 2/11/2026 (AM) | 02/11/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/11/2026
Visual final still needed for installation of motors for air dampers on 1st floor. Still need documentation for chiller startup, boiler startup, and documentation of where and what type of refrigerant leak detection was installed.
|
||||