PRMH202500232
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Partial Pass | 4/25/2025 (12:30 - 2:30) | 4/25/2025 (PM) | 04/25/2025 |
| underground rough-in | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
04/25/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/6/2025 (10:00 - 12:00) | 5/6/2025 (AM) | 05/06/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/06/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
05/06/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/14/2025 (8:00 - 10:00) | 5/14/2025 (AM) | 05/14/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/14/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
05/14/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
05/14/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/19/2025 (10:00 - 12:00) | 5/19/2025 (AM) | 05/19/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/19/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
05/19/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
05/19/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Carried Forward
05/19/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
| Mechanical Final Inspection | Partial Pass | 6/2/2025 (8:00 - 10:00) | 6/2/2025 (AM) | 06/04/2025 |
| Rink 1-final piping | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
06/04/2025
Ice Rink 1 air test on all piping, header and grid pass. Concrete pour on Tuesday
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/11/2025 (10:00 - 12:00) | 6/11/2025 (AM) | 06/11/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/11/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
06/11/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
06/11/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Carried Forward
06/11/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
|
Miscellaneous/Other
Carried Forward
06/11/2025
6/11- Rink 2 melt grid and mains test pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/20/2025 (12:30 - 2:30) | 6/20/2025 (PM) | 06/20/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/20/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
06/20/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
06/20/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Carried Forward
06/20/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
|
Miscellaneous/Other
Carried Forward
06/20/2025
6/11- Rink 2 melt grid and mains test pass
|
||||
|
Miscellaneous/Other
Carried Forward
06/20/2025
6/20- Rink #2 6” underground and rink grid piping 100 PSI test pass, ready for pour.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/26/2025 |
| .3 for subfloor and snow melt | ||||
|
Corrections:
Miscellaneous/Other
Carried Forward
06/26/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
6/11- Rink 2 melt grid and mains test pass
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
6/20- Rink #2 6” underground and rink grid piping 100 PSI test pass, ready for pour.
|
||||
|
Miscellaneous/Other
Carried Forward
06/26/2025
6/26-4-3” mains from chiller room to Rink 3. 100 psi air test pass
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/27/2025 (10:00 - 12:00) | 6/27/2025 (AM) | 06/27/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/27/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
6/11- Rink 2 melt grid and mains test pass
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
6/20- Rink #2 6” underground and rink grid piping 100 PSI test pass, ready for pour.
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
6/26-4-3” mains from chiller room to Rink 3. 100 psi air test pass
|
||||
|
Miscellaneous/Other
Carried Forward
06/27/2025
6/27- 6” underground mains from mechanical room to Rink-3. 100 psi test pass.
|
||||
| Mechanical Rough-in Inspection | Passed | 8/14/2025 (8:00 - 10:00) | 8/14/2025 (AM) | 08/14/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/14/2025
4/25- 100 PSI air test on underground piping from equipment room. Will inspect insulation Monday morning.
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
6/6- 100 PSI test on main underground fusion pipe from equipment room room to Rink #1 header location-Pass test
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
5/14 100 PSI hydrostatic test on underground piping from Rink 2 mechanical room to ice sheet header location PASS
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
5/10- Rink #1 3” piping, headers and tubing. 100 psi hydrostatic test pass.
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
6/11- Rink 2 melt grid and mains test pass
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
6/20- Rink #2 6” underground and rink grid piping 100 PSI test pass, ready for pour.
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
6/26-4-3” mains from chiller room to Rink 3. 100 psi air test pass
|
||||
|
Miscellaneous/Other
Resolved
08/14/2025
6/27- 6” underground mains from mechanical room to Rink-3. 100 psi test pass.
|
||||
|
Miscellaneous/Other
Comment Only
08/14/2025
In floor piping for old labled rink #3 now labled as new rink #1.
All tie-in's, piping for headers and rink, 100 lbs psi holding for all piping... approved
|
||||
| Mechanical Rough-in Inspection | Passed | 8/19/2025 (10:00 - 12:00) | 8/19/2025 (AM) | 08/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/19/2025
Pressure test holding at 100psi for... Rink 1, snow melt mains, subfloor mains and rink mains for piping up to south flex connections.
|
||||
| Mechanical Final Inspection | Passed | 8/25/2025 (8:00 - 10:00) | 8/25/2025 (AM) | 08/25/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/25/2025
Ice Rink 1 air test on all piping, header and grid pass. Concrete pour on Tuesday
|
||||
|
Miscellaneous/Other
Comment Only
08/25/2025
Rink 3 top cooling mat , piping as per design and air test holding at 100psi.... approved
|
||||
| Mechanical Final Inspection | Not Ready | 9/8/2025 (12:30 - 2:30) | 9/8/2025 (PM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2025
See progress inspection dated 9/8, not ready for final inspection at this time.
|
||||
| Progress Inspection | Passed | 11/4/2025 (8:00 - 10:00) | 11/4/2025 (AM) | 11/04/2025 |
| Glycol piping | ||||
|
Corrections:
Miscellaneous/Other
Resolved
11/04/2025
Rink 3 snow melt piping and air test holding at 100 psi.. . approved
|
||||
|
Miscellaneous/Other
Comment Only
11/04/2025
Air test on all chiller piping to roof and in chiller room holding at 100psi... approved
|
||||
| Mechanical Final Inspection | Passed | 1/14/2026 (Afternoon) | 1/14/2026 (PM) | 01/14/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/14/2026
Ammonia monitoring system has been tested, system is functioning as per the system design. All system alarms, shutdowns, exhaust fans, and sensors have been tested and are fully functioning.
Final for this permit approved.
|
||||