PRMH202500861
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 2/21/2025 (10:00 - 12:00) | 2/21/2025 (AM) | 02/24/2025 |
Mechanical Rough-in Inspection | Partial Pass | 3/21/2025 (12:30 - 2:30) | 3/21/2025 (PM) | 03/21/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
03/21/2025
Above hardlide ceiling pass
|
||||
Mechanical Rough-in Inspection | Passed | 4/7/2025 (10:00 - 12:00) | 4/7/2025 (AM) | 04/07/2025 |
Corrections:
Miscellaneous/Other
Outstanding
03/21/2025
Above hardlide ceiling pass
|
||||
Mechanical Final Inspection | Passed | 4/7/2025 (10:00 - 12:00) | 4/7/2025 (AM) | 04/07/2025 |