PRMH202500954
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Partial Pass | 3/18/2025 (10:00 - 12:00) | 3/18/2025 (AM) | 03/20/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
03/20/2025
90% rough in complete, see balance on above ceiling inspection
|
||||
Mechanical Rough-in Inspection | Passed | 3/26/2025 (12:30 - 2:30) | 3/26/2025 (PM) | 03/27/2025 |
Corrections:
Miscellaneous/Other
Outstanding
03/20/2025
90% rough in complete, see balance on above ceiling inspection
|
||||
Miscellaneous/Other
Outstanding
03/27/2025
Rough in complete
|
||||
Mechanical Final Inspection | Not Ready | 4/15/2025 (12:30 - 2:30) | 4/15/2025 (PM) | 04/15/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/15/2025
Not all diffusers in due to furniture in rooms. Call for re-inspection. Thank you, Rob
|
||||
Mechanical Final Inspection | Passed | 4/25/2025 (12:30 - 2:30) | 4/25/2025 (PM) | 04/25/2025 |
Corrections:
Miscellaneous/Other
Outstanding
04/15/2025
Not all diffusers in due to furniture in rooms. Call for re-inspection. Thank you, Rob
|