PRMH202501632
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Not Ready | 8/28/2025 (12:30 - 2:30) | 8/28/2025 (PM) | 08/28/2025 |
| canceled same day; will call back when ready. vm 8/28 | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/28/2025
Inspection canceled by contractor.
|
||||
| Mechanical Final Inspection | Not Ready | 8/28/2025 (12:30 - 2:30) | 8/28/2025 (PM) | 08/28/2025 |
| canceled same day; will call back when ready. vm 8/28 | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/28/2025
Inspection canceled by contractor
|
||||
| Mechanical Rough-in Inspection | Passed | 10/21/2025 (8:00 - 10:00) | 10/21/2025 (AM) | 10/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/21/2025
Unit install and connections... approved
|
||||
| Mechanical Final Inspection | Passed | 10/21/2025 (8:00 - 10:00) | 10/21/2025 (AM) | 10/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/21/2025
Testing of unit shutdown and start up with fire panel in test mode... approved
|
||||