PRMH202501633
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Final Inspection | Pending | |||
Mechanical Rough-in Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
04/17/2025
4/15 duct ok to insulate, VAV’s coming soon.heating piping tested to 100 PSI ready for insulation. Partial Pass
|
||||
Miscellaneous/Other
Outstanding
04/17/2025
4/17- Bathroom exhaust rough in 2nd floor woman’s bathroom. Duct ready for insulation wrap.
|
||||
Mechanical Rough-in Inspection | Partial Pass | 4/15/2025 (10:00 - 12:00) | 4/15/2025 (AM) | 04/15/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/15/2025
4/15 duct ok to insulate, VAV’s coming soon.heating piping tested to 100 PSI ready for insulation. Partial Pass
|
||||
Mechanical Rough-in Inspection | Partial Pass | 4/17/2025 (2:30 - 3:30) | 4/17/2025 (PM) | 04/17/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
04/17/2025
4/15 duct ok to insulate, VAV’s coming soon.heating piping tested to 100 PSI ready for insulation. Partial Pass
|
||||
Miscellaneous/Other
Carried Forward
04/17/2025
4/17- Bathroom exhaust rough in 2nd floor woman’s bathroom. Duct ready for insulation wrap.
|