PRMH202502198
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Final Inspection | Pending | |||
| Mechanical Rough-in Inspection | Pending | 6/27/2025 (2:30 - 3:30) | ||
| Mechanical Rough-in Inspection | Passed | 8/19/2025 (8:00 - 10:00) | 8/19/2025 (AM) | 08/19/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/19/2025
Viewed chilled water piping and hot water piping at tie in's in both penthouses.
Piping is in process of insulation for the chilled water piping.
|
||||
| Mechanical Rough-in Inspection | Passed | 9/15/2025 (12:30 - 2:30) | 9/15/2025 (PM) | 09/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2025
Main floor area A.... remainder of ducting and VAV installation and hookup. Piping connected and tested for leaks.
Approved
|
||||
| Mechanical Rough-in Inspection | Passed | 11/24/2025 (8:00 - 10:00) | 11/24/2025 (AM) | 11/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/24/2025
Main level area A.... air test of mains for fin tube heating holding at 55 psi... approved
|
||||
| Progress Inspection | Passed | 01/22/2026 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
01/22/2026
Air test on hydronic piping holding at 85#... this is the next phase of the building being worked on.
|
||||
| Mechanical Air Test Inspection | Passed | 04/08/2026 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
04/08/2026
80psi air test holding on the mains and branch lines for the fin tube radiator system... approved
|
||||