PRMH202502441
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Final Inspection | Pending | |||
| Mechanical Rough-in Inspection | Partial Pass | 5/16/2025 (10:00 - 12:00) | 5/16/2025 (AM) | 05/16/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/16/2025
5/16- Duct work rough-in entry are ready to be insulated as soon as a few fittings arrive, installation workmanship is excellent.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 5/21/2025 (12:30 - 2:30) | 5/21/2025 (PM) | 05/21/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
05/21/2025
5/16- West duct work rough-in entry are ready to be insulated as soon as a few fittings arrive, installation workmanship is excellent.
|
||||
|
Miscellaneous/Other
Carried Forward
05/21/2025
5/21-West ductwork rough in complete, proceeding with duct insulation.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 6/3/2025 (8:00 - 10:00) | 6/3/2025 (AM) | 06/03/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
06/03/2025
5/16- West duct work rough-in entry are ready to be insulated as soon as a few fittings arrive, installation workmanship is excellent.
|
||||
|
Miscellaneous/Other
Carried Forward
06/03/2025
5/21-West ductwork rough in complete, proceeding with duct insulation.
|
||||
|
Miscellaneous/Other
Carried Forward
06/03/2025
6/3- East ductwork on south entrance is approved for duct insulation.
|
||||
| Mechanical Rough-in Inspection | Partial Pass | 7/8/2025 (10:00 - 12:00) | 7/8/2025 (AM) | 07/11/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
07/11/2025
5/16- West duct work rough-in entry are ready to be insulated as soon as a few fittings arrive, installation workmanship is excellent.
|
||||
|
Miscellaneous/Other
Carried Forward
07/11/2025
5/21-West ductwork rough in complete, proceeding with duct insulation.
|
||||
|
Miscellaneous/Other
Carried Forward
07/11/2025
6/3- East ductwork on south entrance is approved for duct insulation.
|
||||
|
Miscellaneous/Other
Carried Forward
07/11/2025
7/8- 70 of ductwork is roughed in. All VAV’s installed in west entry area.
|
||||
| Mechanical Rough-in Inspection | Passed | 8/12/2025 (10:00 - 12:00) | 8/12/2025 (AM) | 08/12/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/12/2025
5/16- West duct work rough-in entry are ready to be insulated as soon as a few fittings arrive, installation workmanship is excellent.
|
||||
|
Miscellaneous/Other
Resolved
08/12/2025
5/21-West ductwork rough in complete, proceeding with duct insulation.
|
||||
|
Miscellaneous/Other
Resolved
08/12/2025
6/3- East ductwork on south entrance is approved for duct insulation.
|
||||
|
Miscellaneous/Other
Resolved
08/12/2025
7/8- 70 of ductwork is roughed in. All VAV’s installed in west entry area.
|
||||
|
Miscellaneous/Other
Comment Only
08/12/2025
Duct install at NE corner shaft .... approved
|
||||
| Above Ceiling Inspection | Passed | 9/8/2025 (10:00 - 12:00) | 9/8/2025 (AM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2025
Above ceiling area A.
Ducting at mezzanine "Shaft".
20" ducts from mezzanine to locker rooms.
Exposed insulated roof ducting areas D &E
Area C&D at mezzanine above ceiling
Main level and mezzanine level bathroom exhaust ducting and ceiling connections.
|
||||
| Progress Inspection | Passed | 09/12/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
09/12/2025
RI ducting in mezz level refrigeration room... approved
|
||||
| Progress Inspection | Passed | 9/12/2025 (8:00 - 10:00) | 9/12/2025 (AM) | 09/12/2025 |
| Air test | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
09/12/2025
Gas piping and air test to all rooftop units holding at 30psi... approved
|
||||
| Mechanical Rough-in Inspection | Not Ready | 9/15/2025 (10:00 - 12:00) | 9/15/2025 (AM) | 09/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2025
Inspection canceled by contractor, already lookedat ducting that was ready for inspection on 9/12
|
||||
| Progress Inspection | Passed | 9/18/2025 (2:30 - 3:30) | 9/18/2025 (PM) | 09/18/2025 |
| Grease duct inspection | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
09/18/2025
Kitchen hood, grease duct light test performed to test for any pin holes in welds. All welds are fine and test approved.
|
||||
| Mechanical Final Inspection | Partial Pass | 9/29/2025 (8:00 - 10:00) | 9/29/2025 (AM) | 09/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/29/2025
Mechanical final for system operations to allow use of parts of the building approved.
Final is pending the completion of equipment install and tie-in at the mechanical room, hood test at the kitchen, and balance report of building.
|
||||
| Mechanical Final Inspection | Partial Pass | 11/19/2025 (12:30 - 2:30) | 11/19/2025 (PM) | 11/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/19/2025
Ducting hookup to the installed unit... ok to insulate.
Capture test for kitchen hood... approved.
Set up final inspection to test units for shutdown upon smoke detector activation.
|
||||