PRMH202504795
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Mechanical Rough-in Inspection | Passed | 5/14/2025 (10:00 - 12:00) | 5/14/2025 (AM) | 05/14/2025 |
Corrections:
Miscellaneous/Other
Outstanding
05/14/2025
No answer at number, went inside. Rough in /above ceiling is a pass.
|
||||
Mechanical Rough-in Inspection | Passed | 6/10/2025 (8:00 - 10:00) | 6/10/2025 (AM) | 06/10/2025 |
Mechanical Final Inspection | Passed | 6/23/2025 (8:00 - 10:00) | 6/23/2025 (AM) | 06/23/2025 |
Corrections:
Miscellaneous/Other
Outstanding
06/23/2025
Please send balance report to city. Thank you,Rob
|