PRMH202508893
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Passed | 9/2/2025 (10:00 - 12:00) | 9/2/2025 (AM) | 09/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2025
Light test at grease hood/ ducting ... approved
|
||||
| Mechanical Final Inspection | Partial Pass | 9/16/2025 (8:00 - 10:00) | 9/16/2025 (AM) | 09/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/16/2025
Partial pass on this mechanical for this space.
Full Final inspection is pending a capture test of the hood and viewing of the grease duct wrap.
|
||||
| Mechanical Final Inspection | Passed | 11/6/2025 (2:30 - 3:30) | 11/6/2025 (PM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
Capture test performed at hood, contractor will rebalance to ramp up hood. ... final approved
|
||||