PRMH202509176
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Passed | 9/8/2025 (8:00 - 10:00) | 9/8/2025 (AM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2025
RI ducting approved, ok to insulate
|
||||
| Mechanical Final Inspection | Passed | 10/3/2025 (12:30 - 2:30) | 10/3/2025 (PM) | 10/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/03/2025
Final approved
|
||||