| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Mechanical Rough-in Inspection | Passed | 3/3/2026 (8:00 - 10:00) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
Equipment venting hookup... approved
|
||||
| Mechanical Final Inspection | Passed | 3/3/2026 (8:00 - 10:00) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
Final for this quarterly permit of area B... approved
|
||||