PRPL201700071
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 10/6/2017 (8:00 - 10:00) | 3/6/2017 | 03/06/2017 |
In wall rough in o.k. To cover | ||||
Plumbing Final Inspection | Partial Pass | 4/7/2017 | 04/10/2017 | |
Plumbing Rough-in Inspection | Passed | 5/18/2017 (10:00 - 12:00) | 5/18/2017 | 05/18/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/18/2017
Phase1 rough in complete. Ok to cover walls. One bathroom, five exam room sinks.
|
||||
Plumbing Rough-in Inspection | Passed | 5/26/2017 (12:30 - 2:30) | 5/26/2017 | 05/26/2017 |
Inwall RI ok in prep room 3 sinks | ||||
Plumbing Final Inspection | Passed | 7/7/2017 (2:30 - 3:30) | 7/7/2017 | 07/07/2017 |
Fixtures set and sealed-manometer holds | ||||
Plumbing Final Inspection | VOID | 4/7/2017 (12:30 - 2:30) | 4/7/2017 | 09/11/2018 |