Permit Application Status

PRPL201700498


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201700498
Plumbing
Finaled
STATION LLC
New
Plumbing work for new 7-story parking ramp with lower level enclosed garage.
02/13/2017
02/21/2017
04/18/2018
10/20/2017

Locations

Permits

Permit Number: PRPL201700498

Plumbing
Finaled
02/21/2017
04/18/2018

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 3/28/2017 (2:30 - 3:30) 3/28/2017 03/28/2017
Corrections:


Miscellaneous/Other
Carried Forward
03/28/2017
Air tests on partial underground sanitary sewer and storm sewer south side of building.

Plumbing Rough-in Inspection Passed 4/19/2017 (10:00 - 12:00) 4/19/2017 04/19/2017
Corrections:


Miscellaneous/Other
Comment Only
04/19/2017
Air tests on partial underground sanitary sewer and storm sewer south side of building. 4-19-2017. Visual on piping for elevator drain pan. Future airtest.

Plumbing Rough-in Inspection Partial Pass 6/22/2017 (12:30 - 2:30) 6/22/2017 06/22/2017
Corrections:


Miscellaneous/Other
Comment Only
06/22/2017
North and South underground flam waste and storm. Columns B3-B9. 5# ok to cover

Plumbing Rough-in Inspection Passed w/ Conditions 6/26/2017 (12:30 - 2:30) 6/26/2017 06/26/2017
Corrections:


Miscellaneous/Other
Comment Only
06/26/2017
Underground- New Parking ramp. A) Lowest bsmt level at North east corner from water sprinkler room to B-line east center column area. B) Pipe type 4 inch schedule 40 PVC with /clean outs. C) Pipe slope 1/8 inch, per lin ft. measured using 2 ft digital level by inspector, approved per exception 708.1. D) All parking ramp floor drains must first terminate into accessible flammable waste traps, prior to entering storm sewer. E) 4 psi air.

Plumbing Rough-in Inspection Partial Pass 7/17/2017 (8:00 - 10:00) 7/17/2017 07/17/2017
Corrections:


Miscellaneous/Other
Comment Only
07/17/2017
Air test holding at 5 psi on piping run from floor drain and clean out from water meter room, and east piping on waste and rain leader grid B3-B9 ....Ok to cover piping.

Plumbing Rough-in Inspection Passed w/ Conditions 7/18/2017 (2:30 - 3:30) 7/18/2017 07/19/2017
Plumbing Rough-in Inspection Partial Pass 7/21/2017 (10:00 - 12:00) 7/21/2017 07/21/2017
Corrections:


Miscellaneous/Other
Comment Only
07/21/2017
5lb air test on lower lever waste to flammable waste tank. Rainwater underground services 1st and 2nd level. Water meter room drain piping. All on 5lb test. Monomer test on flammable waste tank holding at 1 inch. Approved to cover.

Plumbing Rough-in Inspection Partial Pass 7/24/2017 (12:30 - 2:30) 7/24/2017 07/24/2017
Corrections:


Miscellaneous/Other
Comment Only
07/24/2017
5psi air test on drain line from East elevator pit piping. Approved to cover. Pictures also viewed.

Plumbing Rough-in Inspection Partial Pass 7/27/2017 (10:00 - 12:00) 7/27/2017 07/27/2017
Corrections:


Miscellaneous/Other
Comment Only
07/27/2017
5# air on 18 and 12 storm, also 8" sanitary in pump/ basket room- Southeast corner-underground ok to cover

Plumbing Rough-in Inspection Partial Pass 8/11/2017 (10:00 - 12:00) 8/11/2017 08/11/2017
Corrections:


Miscellaneous/Other
Comment Only
08/11/2017
3# air on "B" column 3rd through 7th

Miscellaneous/Other
Outstanding
08/11/2017

Plumbing Rough-in Inspection Partial Pass 08/22/2017
Corrections:


Miscellaneous/Other
Comment Only
08/22/2017
Air test on: grid D3 upper piping, grid B short stacks

Plumbing Rough-in Inspection Passed 8/31/2017 (12:30 - 2:30) 8/31/2017 08/31/2017
Corrections:


Miscellaneous/Other
Comment Only
08/31/2017
Air on complete system ok-will see final visual inspection once street is tied in

Plumbing Final Inspection Passed 10/19/2017 (2:30 - 3:30) 10/19/2017 10/20/2017
Corrections:


Miscellaneous/Other
Comment Only
10/20/2017
Ramp plumbing complete.