PRPL201700498
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 3/28/2017 (2:30 - 3:30) | 3/28/2017 | 03/28/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
03/28/2017
Air tests on partial underground sanitary sewer and storm sewer south side of building.
|
||||
Plumbing Rough-in Inspection | Passed | 4/19/2017 (10:00 - 12:00) | 4/19/2017 | 04/19/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2017
Air tests on partial underground sanitary sewer and storm sewer south side of building.
4-19-2017. Visual on piping for elevator drain pan. Future airtest.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/22/2017 (12:30 - 2:30) | 6/22/2017 | 06/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/22/2017
North and South underground flam waste and storm. Columns B3-B9. 5# ok to cover
|
||||
Plumbing Rough-in Inspection | Passed w/ Conditions | 6/26/2017 (12:30 - 2:30) | 6/26/2017 | 06/26/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/26/2017
Underground- New Parking ramp. A) Lowest bsmt level at North east corner from water sprinkler room to B-line east center column area. B) Pipe type 4 inch schedule 40 PVC
with /clean outs. C) Pipe slope 1/8 inch, per lin ft. measured using 2 ft digital level by inspector, approved per exception 708.1. D) All parking ramp floor drains must first terminate into accessible flammable waste traps, prior to entering storm sewer. E) 4 psi air.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/17/2017 (8:00 - 10:00) | 7/17/2017 | 07/17/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/17/2017
Air test holding at 5 psi on piping run from floor drain and clean out from water meter room, and east piping on waste and rain leader grid B3-B9 ....Ok to cover piping.
|
||||
Plumbing Rough-in Inspection | Passed w/ Conditions | 7/18/2017 (2:30 - 3:30) | 7/18/2017 | 07/19/2017 |
Plumbing Rough-in Inspection | Partial Pass | 7/21/2017 (10:00 - 12:00) | 7/21/2017 | 07/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/21/2017
5lb air test on lower lever waste to flammable waste tank. Rainwater underground services 1st and 2nd level. Water meter room drain piping. All on 5lb test. Monomer test on flammable waste tank holding at 1 inch. Approved to cover.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/24/2017 (12:30 - 2:30) | 7/24/2017 | 07/24/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/24/2017
5psi air test on drain line from East elevator pit piping. Approved to cover. Pictures also viewed.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/27/2017 (10:00 - 12:00) | 7/27/2017 | 07/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2017
5# air on 18 and 12 storm, also 8" sanitary in pump/ basket room- Southeast corner-underground ok to cover
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/11/2017 (10:00 - 12:00) | 8/11/2017 | 08/11/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/11/2017
3# air on "B" column 3rd through 7th
|
||||
Miscellaneous/Other
Outstanding
08/11/2017
|
||||
Plumbing Rough-in Inspection | Partial Pass | 08/22/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/22/2017
Air test on: grid D3 upper piping, grid B short stacks
|
||||
Plumbing Rough-in Inspection | Passed | 8/31/2017 (12:30 - 2:30) | 8/31/2017 | 08/31/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2017
Air on complete system ok-will see final visual inspection once street is tied in
|
||||
Plumbing Final Inspection | Passed | 10/19/2017 (2:30 - 3:30) | 10/19/2017 | 10/20/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/20/2017
Ramp plumbing complete.
|