PRPL201701037
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Final Inspection | Partial Pass | 07/06/2017 | ||
Plumbing Rough-in Inspection | Passed | 3/28/2017 (10:00 - 12:00) | 3/28/2017 | 07/06/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
03/28/2017
Air test on all waste vent and water passages. Tape or insulate water pipe where touching studs. Cut 3/8 inch rods on copper tear drop water pipe hangers for insulation to fit. Secure 1/2 inch hot water riser on lav in women's room.
|
||||
Miscellaneous/Other
Outstanding
03/28/2017
Previous comments were for 4 th floor. Same comments for fifth floor. Secure water risers. Both floors move waterhammer arrestors to a location between last 2 flushometer valves in all bathrooms. Allaitests on 5th floor approved.
|
||||
Plumbing Rough-in Inspection | Passed | 7/6/2017 (8:00 - 10:00) | 7/6/2017 (AM) | 07/06/2017 |
4th floor final | ||||
Corrections:
Miscellaneous/Other
Outstanding
03/28/2017
Air test on all waste vent and water passages. Tape or insulate water pipe where touching studs. Cut 3/8 inch rods on copper tear drop water pipe hangers for insulation to fit. Secure 1/2 inch hot water riser on lav in women's room.
|
||||
Plumbing Final Inspection | Passed | 7/17/2017 (2:30 - 3:30) | 7/17/2017 | 07/17/2017 |