PRPL201701179
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 4/4/2017 (2:30 - 3:30) | 3/9/2017 (AM) | 03/09/2017 |
March 7, 2017. Informational inspection and visual in spection on waste, vent and water piping in the 12th floor mens and womens bathrooms . | ||||
Plumbing Rough-in Inspection | VOID | 03/09/2017 | ||
Plumbing Rough-in Inspection | Partial Pass | 3/23/2017 (10:00 - 12:00) | 3/23/2017 | 03/23/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
03/23/2017
Waste and vent air test on leaves in women's restrooms on floors 11-9 approved
|
||||
Plumbing Rough-in Inspection | Partial Pass | 3/29/2017 (2:30 - 3:30) | 3/29/2017 | 03/29/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
03/29/2017
Waste and vent air test on leaves in women's restrooms on floors 11-9 approved
|
||||
Plumbing Rough-in Inspection | Partial Pass | 3/27/2017 | 04/05/2017 | |
Corrections:
Miscellaneous/Other
Comment Only
04/05/2017
Manometer on flammable waste and sump tanks approved.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/4/2017 (2:30 - 3:30) | 4/4/2017 | 04/06/2017 |
Corrections:
Miscellaneous/Other
Outstanding
03/29/2017
Waste and vent air test on leaves in women's restrooms on floors 11-9 approved.
Waste and vent stacks for floors 2-11 airtested and approved.
Lav in wall rough in completed on 8-10.
Visual on ug sanitary and flammable waste lines on loading dock ok - drains will be set and be airtested.
Final on 12 th floor men's and women's.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/6/2017 (10:00 - 12:00) | 4/6/2017 | 04/06/2017 |
Plumbing Rough-in Inspection | Passed | 4/12/2017 (8:00 - 10:00) | 4/12/2017 | 04/12/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/12/2017
Airtest on sanitary and flammable wastes to ranks in loading dock area ok
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/19/2017 (10:00 - 12:00) | 4/19/2017 | 04/19/2017 |
All floors - Lav risers | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/19/2017
Airtest on entire stack of lavatories on south side.
|
||||
Plumbing Rough-in Inspection | Passed | 4/21/2017 (10:00 - 12:00) | 4/21/2017 | 04/24/2017 |
Corrections:
Miscellaneous/Other
Comment Only
04/21/2017
Jmiller@schadegg-Mech.com
|
||||
Miscellaneous/Other
Comment Only
04/21/2017
Northside 10rh floor men's room right in
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/1/2017 (8:00 - 10:00) | 5/1/2017 | 05/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/01/2017
Airtest on waste and vent, men's and women's 1oth floor bathrooms.
Extend sanitary waste for water closets to an accessible clean out in all bathrooms per code.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/12/2017 (12:30 - 2:30) | 5/12/2017 | 05/12/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2017
Airtest on 9th floor complete.
|
||||
Plumbing Rough-in Inspection | Passed | 5/22/2017 (12:30 - 2:30) | 5/22/2017 | 05/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2017
Airtest on venting for 5 floor drains in boiler room. Visual on discharge of flammable waste rank. Visual on waste line for storm drain sump.
|
||||
Plumbing Rough-in Inspection | Passed | 5/31/2017 (8:00 - 10:00) | 5/31/2017 | 05/31/2017 |
Plumbing Rough-in Inspection | Passed | 6/16/2017 (8:00 - 10:00) | 6/16/2017 | 06/19/2017 |
8th floor | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/16/2017
Final on 9th floor and demo on 8th floor. Starting demo on 13th floor.
|
||||
Plumbing Final Inspection | Partial Pass | 6/21/2017 (10:00 - 12:00) | 6/21/2017 | 06/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/21/2017
Outdoor chiller 6 drains 5# ok to cover
|
||||
Plumbing Rough-in Inspection | Passed | 6/27/2017 (8:00 - 10:00) | 6/27/2017 | 06/27/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/27/2017
13th floor men's and women's bathrooms rough in air tests ok yo cover.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/30/2017 (12:30 - 2:30) | 6/30/2017 | 06/30/2017 |
Corrections:
Miscellaneous/Other
Comment Only
06/30/2017
7th floor south , air test on drain piping holding at 5lbs. Approved
|
||||
Plumbing Rough-in Inspection | Passed | 7/5/2017 (12:30 - 2:30) | 7/5/2017 (PM) | 07/06/2017 |
R.I. for 7th floor mens room. | ||||
Plumbing Final Inspection | Passed | 7/24/2017 (12:30 - 2:30) | 7/24/2017 | 07/25/2017 |
Corrections:
Miscellaneous/Other
Comment Only
07/25/2017
8th floor final on bathrooms approved.
13th floor finals on bathrooms approved.
|
||||
Plumbing Rough-in Inspection | Passed | 8/4/2017 (12:30 - 2:30) | 8/4/2017 | 08/07/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/04/2017
6th floor rough-in airtests approved to cover.
|
||||
Plumbing Final Inspection | Passed | 8/9/2017 (12:30 - 2:30) | 8/9/2017 | 08/09/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/09/2017
7th floor final.
|
||||
Plumbing Rough-in Inspection | Passed | 8/14/2017 (12:30 - 2:30) | 8/14/2017 | 08/15/2017 |
Plumbing Rough-in Inspection | Passed | 8/25/2017 (10:00 - 12:00) | 8/25/2017 | 08/25/2017 |
Plumbing Final Inspection | Partial Pass | 9/13/2017 (8:00 - 10:00) | 9/13/2017 | 09/13/2017 |
Corrections:
Miscellaneous/Other
Outstanding
09/13/2017
6th floor not completed. Re inspection required for 3 lavs in men's room, drinking fountain, and countertop sink in secondary room.
Bsmt barhrooms ok
Bring absurd requirements for eyewash station and reinspect.
Caulk laundry tub to wall.
R.P.Z. Installed. Please take out a permit for installation and testing.
Please pass on comments to Kirk.
|
||||
Plumbing Rough-in Inspection | Passed | 9/22/2017 (10:00 - 12:00) | 9/22/2017 | 09/22/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2017
14th floor men's room all air tested. 6th floor mother's room sink, water coolers and lavs all completed.
|
||||
Plumbing Rough-in Inspection | Passed | 9/29/2017 (12:30 - 2:30) | 9/29/2017 | 10/01/2017 |
Plumbing Rough-in Inspection | Passed | 10/4/2017 (8:00 - 10:00) | 10/4/2017 | 10/04/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/04/2017
4th floor rough in airtest in men’s and women’s last week.
5th floor final in men’s and women’s.
|
||||
Plumbing Rough-in Inspection | Passed | 10/17/2017 (12:30 - 2:30) | 10/17/2017 | 10/18/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2017
4th floor rough in, 3rd floor final approved.
|
||||
Plumbing Rough-in Inspection | Passed | 10/26/2017 (12:30 - 2:30) | 10/26/2017 | 10/26/2017 |
Plumbing Rough-in Inspection | Passed | 10/25/2017 (10:00 - 12:00) | 10/25/2017 | 10/26/2017 |
Plumbing Rough-in Inspection | Passed | 10/30/2017 (12:30 - 2:30) | 10/30/2017 | 10/30/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2017
Visual final on 4th floor bathrooms approved.
|
||||
Plumbing Rough-in Inspection | Passed | 11/15/2017 (8:00 - 10:00) | 11/15/2017 | 11/15/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2017
1st floor rough in complete 5# ok
|
||||
Plumbing Final Inspection | Not Ready | 11/28/2017 (8:00 - 10:00) | 11/28/2017 | 11/28/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/28/2017
Not ready
|
||||
Plumbing Rough-in Inspection | Partial Pass | 11/30/2017 (12:30 - 2:30) | 11/30/2017 | 12/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2017
3rd floor north and south rest rooms final inspection-fixtures set and sealed
|
||||
Plumbing Rough-in Inspection | Partial Pass | 12/7/2017 (12:30 - 2:30) | 12/7/2017 | 12/08/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/08/2017
2nd floor final
|
||||
Plumbing Final Inspection | Passed | 12/15/2017 (12:30 - 2:30) | 12/15/2017 | 12/15/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2017
Job complete-final passed
|
||||
Plumbing Rough-in Inspection | VOID | 09/11/2018 |