PRPL201703975
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 8/1/2017 (8:00 - 10:00) | 8/1/2017 | 08/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/01/2017
5# on complete underground sanitary-ok to cover. Flam. waste also tested. Mechanical room underground tested. Greg to stub future 4" waste line in for new trash room on existing building.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/21/2017 (10:00 - 12:00) | 8/21/2017 | 08/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
08/21/2017
5# on 4" pvc running from existing building to new building. Clean outs installed, foam covering pipe. Plumber to update drawings
|
||||
Plumbing Rough-in Inspection | Passed | 9/13/2017 (12:30 - 2:30) | 9/13/2017 | 09/13/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/13/2017
Visual inspection of 1st floor waste and vent.
Visual inspection of units 4,6,7 on 2nd floor.
|
||||
Plumbing Rough-in Inspection | Passed | 10/10/2017 (12:30 - 2:30) | 10/10/2017 | 10/10/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/10/2017
All waste and vent airtested from roof to ceiling of garage. Ok to cover.
|
||||
Plumbing Rough-in Inspection | Not Ready | 10/13/2017 (8:00 - 10:00) | 10/13/2017 | 10/13/2017 |
Corrections:
Miscellaneous/Other
Carried Forward
10/13/2017
Inspection rescheduled for Monday. Not enough time scheduled.
|
||||
Plumbing Rough-in Inspection | Passed | 10/16/2017 (2:30 - 3:30) | 10/16/2017 | 10/17/2017 |
Corrections:
Miscellaneous/Other
Outstanding
10/13/2017
Inspection rescheduled for Monday. Not enough time scheduled.
|
||||
Miscellaneous/Other
Comment Only
10/17/2017
Visual walk through. Nail plate, finish fire caulking, support stacks at each story, call for reinspection.
|
||||
Plumbing Rough-in Inspection | Passed | 11/7/2017 (2:30 - 3:30) | 11/7/2017 | 11/08/2017 |
Plumbing Rough-in Inspection | Passed | 12/4/2017 (2:30 - 3:30) | 12/4/2017 | 12/04/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/04/2017
5# on all parking garage above ground piping. 5# on storm as well. Could not find blue sheets in job trailer to update, job sup. and plumbing foreman not aware of a book or any blue sheets.
|
||||
Plumbing Final Inspection | Partial Pass | 1/30/2018 (12:30 - 2:30) | 1/30/2018 | 01/30/2018 |
Corrections:
Miscellaneous/Other
Outstanding
01/30/2018
Dishwasher in 205 not set properly.
Pop-up in 207.
Manometer test approved. First and 2nd floor walk through completed.
Replace Jym caps with blind plugs in the garage.
|
||||
Plumbing Final Inspection | Partial Pass | 2/1/2018 (2:30 - 3:30) | 2/1/2018 | 02/02/2018 |
Plumbing Final Inspection | Passed | 2/28/2018 | 02/28/2018 | |
Corrections:
Comment Only
02/28/2018
Elevator pan drains have been inspected and meet the code and are approved.
|