PRPL201708073
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 9/18/2017 (10:00 - 12:00) | 9/18/2017 | 09/18/2017 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2017
In-wall gas line airtest 30/60 PSI
Airtest on in wall waste/vent/waters for kitchen, family bathroom.
Will add floor drains for hood wash down.
Ok to cover kitchen walls.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/9/2017 (8:00 - 10:00) | 10/09/2017 | |
Corrections:
Miscellaneous/Other
Comment Only
10/09/2017
Airtest on all waste and vent for bathrooms, drinking fountains. mop sink and under floor 4 inch main. Water ok. See underfloor when piping is completed.
All gas line airtested from inwall outlets to where it is stubbed out roof.
|
||||
Plumbing Rough-in Inspection | Passed | 10/16/2017 (12:30 - 2:30) | 10/16/2017 | 10/16/2017 |
Plumbing Rough-in Inspection | Passed | 10/26/2017 | 11/08/2017 | |
Plumbing Rough-in Inspection | Partial Pass | 11/14/2017 (8:00 - 10:00) | 11/14/2017 | 11/15/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2017
Bar RI 5# ok-will see underfloor at later date
|
||||
Plumbing Final Inspection | Partial Pass | 1/29/2018 (8:00 - 10:00) | 1/29/2018 | 01/29/2018 |
Cancelled today, as foreman out sick. jsmidt 01/26/2018 8:03 AM | ||||
Corrections:
Miscellaneous/Other
Comment Only
01/29/2018
Manometer test on east and west public bathrooms, family restroom, D.F., and employee bathrooms, mop sinks.
|
||||
Plumbing Final Inspection | Partial Pass | 4/2/2018 (8:00 - 10:00) | 4/2/2018 | 04/02/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/02/2018
Please reschedule for 1 hour
Thank you
|
||||
Plumbing Final Inspection | Passed | 4/3/2018 (8:00 - 10:00) | 4/3/2018 | 04/03/2018 |