PRPL201708962
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 10/11/2017 (10:00 - 12:00) | 10/11/2017 | 10/11/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/11/2017
2nd floor
Airtest on all inwall waste and vent with the exception of the lavatories.
Will install separate faucet for mop sink soap dispenser.
|
||||
Plumbing Rough-in Inspection | Passed | 10/30/2017 (10:00 - 12:00) | 10/30/2017 | 10/30/2017 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2017
Airtest on waste and vent in ceiling of 1st floor serving 2nd floor bathrooms, D.F.’s and mop sink.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 11/14/2017 (8:00 - 10:00) | 11/14/2017 | 11/14/2017 |
Corrections:
Miscellaneous/Other
Comment Only
11/14/2017
First floor waste and vent 5# ok to cover
|
||||
Plumbing Final Inspection | Partial Pass | 1/9/2018 (8:00 - 10:00) | 1/9/2018 | 01/09/2018 |
Corrections:
Miscellaneous/Other
Comment Only
01/09/2018
2nd floor rest rooms fixtures set and sealed-manometer holds
|
||||
Plumbing Final Inspection | Failed | 2/8/2018 (10:00 - 12:00) | 2/8/2018 | 02/08/2018 |
Corrections:
Miscellaneous/Other
Carried Forward
02/08/2018
Manometer test failure on 1st floor. Resolved. 2-12-18
|
||||
Plumbing Rough-in Inspection | Passed | 2/12/2018 (8:00 - 10:00) | 2/12/2018 | 02/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
02/12/2018
Manometer test on 2 bathrooms on 1st floor. Passed
|