PRPL201711415
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 12/01/2017 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/01/2017
RI ok to cover
|
||||
Plumbing Final Inspection | Not Ready | 12/1/2017 (8:00 - 10:00) | 12/1/2017 | 12/01/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2017
Not ready-this inspection was scheduled in place of a rough in-Mike M updated RI inspection.
|
||||
Plumbing Final Inspection | Passed | 12/20/2017 (10:00 - 12:00) | 12/20/2017 | 12/21/2017 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2017
Fixtures set and sealed-air gap and hammer arrestors installed, Dis to send picture of 1022 device for coffee supply to Mike M
|