PRPL201800119
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 3/22/2018 (8:00 - 10:00) | 3/22/2018 | 03/22/2018 |
Corrections:
Miscellaneous/Other
Comment Only
03/22/2018
5# air on south wing underground sanitary and storm drain. OK to cover. Mike M highlighted the plan in RT Moore’s job trailer.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 3/29/2018 (8:00 - 10:00) | 03/29/2018 | |
Corrections:
Miscellaneous/Other
Comment Only
03/29/2018
Install of elevator sump basket and drain from shaft. Dave Murphy from RT Moore submitted pictures. Pictures attached to permit.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/11/2018 (8:00 - 10:00) | 4/11/2018 | 04/11/2018 |
Corrections:
Miscellaneous/Other
Outstanding
03/29/2018
Received pictures from Dave Murphy at RT Moore of installation of basket and piping for elevator shaft drain. Attached pictures to permit in Cityview. Morehouse Michael 03/29/2018 12:24 PM
|
||||
Miscellaneous/Other
Comment Only
04/11/2018
Underground sanitary to grid line H-5# ok to cover-pool sumo basket ok
|
||||
Plumbing Rough-in Inspection | Passed | 4/13/2018 (8:00 - 10:00) | 4/13/2018 | 04/13/2018 |
Plumbing Rough-in Inspection | Passed | 4/18/2018 (12:30 - 2:30) | 4/18/2018 | 04/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/18/2018
U.g. Airtest for stacks every 8 feet.
Airtest on remaining storm drain.
|
||||
Plumbing Rough-in Inspection | Passed | 4/20/2018 (12:30 - 2:30) | 4/20/2018 | 04/20/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/20/2018
Airtest on remainder of sanitary going out of the building.
|
||||
Plumbing Rough-in Inspection | Passed | 4/24/2018 (12:30 - 2:30) | 4/24/2018 | 04/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/24/2018
Remainder of 8” storm drain airtested.
|
||||
Plumbing Rough-in Inspection | Passed | 4/27/2018 (12:30 - 2:30) | 4/27/2018 | 04/27/2018 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2018
Airtest on kitchen and laundry underground
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/18/2018 (12:30 - 2:30) | 10/18/2018 | 10/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2018
Airtest on waste and vent for entire building. Ok. Do not cover before visual inspection.
|
||||
Plumbing Air Test Inspection | Partial Pass | 10/19/2018 (8:00 - 10:00) | 10/19/2018 | 10/19/2018 |
Plumbing Rough-in Inspection | Partial Pass | 10/22/2018 (10:00 - 12:00) | 10/22/2018 | 10/23/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/23/2018
Airtest on 3 rainwater leader overflows
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/23/2018 (10:00 - 12:00) | 10/23/2018 | 10/23/2018 |
Plumbing Rough-in Inspection | Partial Pass | 10/24/2018 (10:00 - 12:00) | 10/24/2018 | 10/24/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/24/2018
5th and 4th floor visual rough in, ok to cover.
All storm drain over flows air tested.
Roof top inspection completed. Bolt down strainer baskets.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/25/2018 (10:00 - 12:00) | 10/25/2018 | 10/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2018
Rough in visual walk through of 2nd and 3rd floors. Nail plates
Ok to cover
|
||||
Plumbing Rough-in Inspection | Passed | 10/26/2018 (Morning) | 10/26/2018 | 10/29/2018 |
Partial Inspection | Partial Pass | 4/4/2019 (10:00 - 12:00) | 4/4/2019 (AM) | 04/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/04/2019
Final walk through of 4th and 5th floors.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/2/2019 (8:00 - 10:00) | 7/2/2019 (AM) | 07/02/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/02/2019
Walk through of rooms on 3rd and 2nd floors. 1st floor mechanical room, commercial laundry. 3 R.P.Z.’s to be tested. Specifications on pumps have been supplied to the elevator inspector.
R. L. Ames will send email to Elevator Inspector Brian Harren.
Cody will email Rebecca the pump specifications.
Plumbers will reconfigure 3 comp sink drainage piping.
|
||||
Plumbing Final Inspection | Partial Pass | 7/12/2019 (2:30 - 3:30) | 7/12/2019 (PM) | 07/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2019
03 stack doesn’t hold, retest.
Manometer tests.
|
||||
Plumbing Final Inspection | Partial Pass | 7/12/2019 (12:30 - 2:30) | 7/12/2019 (PM) | 07/12/2019 |
Plumbing Final Inspection | Partial Pass | 7/15/2019 (2:30 - 3:30) | 7/15/2019 (PM) | 07/16/2019 |
Plumbing Final Inspection | Passed | 7/18/2019 (10:00 - 12:00) | 7/18/2019 (AM) | 07/18/2019 |