PRPL201802108
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Rough-in Inspection | Passed | 3/28/2018 (8:00 - 10:00) | 3/28/2018 | 03/28/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/28/2018
Airtest on ug for foot baths and adjoining bathrooms.
|
||||
| Plumbing Rough-in Inspection | Passed | 5/11/2018 (12:30 - 2:30) | 5/11/2018 | 05/11/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/11/2018
Airtest on all waste and vent, waters ok
Do not cover walls until foot bath and faucet have arrived for installation measurements and specifications. Any Sheetrocking down at owners risk of removal.
Owner supplied fixtures.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 7/18/2018 (10:00 - 12:00) | 7/18/2018 | 07/18/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/18/2018
Foot washing base ok-faucet is single supply, asked to see specs or provisions for mixing valve. No sprayer on the faucet presented to me. Approved lav faucets considering bathrooms were not for use by transient public.
|
||||
| Plumbing Final Inspection | Passed | 9/10/2018 (12:30 - 2:30) | 9/10/2018 | 09/10/2018 |