Permit Application Status

PRPL201803642


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201803642
Plumbing
Finaled
BLMGTN SCHOOL DIST #271
Repair/Replace
Remodel (2) bathrooms and add another.
04/24/2018
04/25/2018
02/18/2019
08/22/2018

Locations

Permits

Permit Number: PRPL201803642

Plumbing
Finaled
04/25/2018
02/18/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Passed 7/2/2018 (10:00 - 12:00) 7/2/2018 07/02/2018
Corrections:


Miscellaneous/Other
Comment Only
07/02/2018
Underground airtest on men’s and women’s back to back main sewer ok to cover.

Underground Plumbing Inspection Passed 7/5/2018 (Afternoon) 7/5/2018 07/05/2018
Corrections:


Miscellaneous/Other
Comment Only
07/05/2018
Airtest on underground for new bathrooms in existing space.

Plumbing Rough-in Inspection Passed 7/23/2018 (12:30 - 2:30) 7/23/2018 07/23/2018
Corrections:


Miscellaneous/Other
Comment Only
07/23/2018
Accessible bathroom waste and vent Airtest. Ok to cover.

Plumbing Rough-in Inspection Passed 7/26/2018 (8:00 - 10:00) 7/26/2018 07/26/2018
Plumbing Final Inspection Partial Pass 8/17/2018 (10:00 - 12:00) 8/17/2018 08/17/2018
Plumbing Final Inspection Passed 8/22/2018 (10:00 - 12:00) 8/22/2018 08/22/2018
Corrections:


Miscellaneous/Other
Comment Only
08/22/2018
Manometer test on single stall back to back accessible bathrooms.