Permit Application Status

PRPL201805907


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201805907
Plumbing
Finaled
MINNEAPOLIS ES HOTEL LLC
Alteration/Remodel
Install new bar and kitchen equipment per engineered plans.
06/13/2018
06/14/2018
04/17/2019
10/19/2018

Locations

Permits

Permit Number: PRPL201805907

Plumbing
Finaled
06/14/2018
04/17/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Passed 7/18/2018 (12:30 - 2:30) 7/18/2018 08/10/2018
Corrections:


Miscellaneous/Other
Comment Only
07/18/2018
5# underground ok to cover. Contractor to submit revised plan with as built drawing to mmorehouse@bloomingtonmn.gov Contractor to abandon existing bar waste line properly.

Plumbing Rough-in Inspection Passed 8/10/2018 (8:00 - 10:00) 8/10/2018 (AM) 08/10/2018
Per Mike Morehouse, told contractor to schedule re-inspect with him. ajacobson 08/08/2018 10:46 AM
Corrections:


Comment Only
08/10/2018
Inwall and ceiling ok to cover 5# ok no mano on final Morehouse Michael 08/10/2018 9:17 AM

Plumbing Final Inspection Passed 10/16/2018 (10:00 - 12:00) 10/16/2018 10/19/2018
Corrections:


Miscellaneous/Other
Comment Only
10/19/2018
Fixtures set and sealed