Summary

PRPL201807411
Plumbing
Expired
MSP BLOOMINGTON LLC
New
Interior plumbing complete for 182 units - new hotel construction.
07/13/2018
08/16/2018
06/28/2020

Locations

Permits

Permit Number: PRPL201807411

Plumbing
Expired
08/16/2018
06/28/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Final Inspection Pending
Plumbing Rough-in Inspection Partial Pass 8/20/2018 (12:30 - 2:30) 8/20/2018 08/20/2018
Corrections:


Miscellaneous/Other
Comment Only
08/20/2018
Airtest on main sanitary sewer.

Plumbing Rough-in Inspection Partial Pass 8/31/2018 (12:30 - 2:30) 8/31/2018 08/31/2018
Corrections:


Miscellaneous/Other
Comment Only
08/31/2018
Airtest on sanitary and storm underground in tru home section, less the pantry.

Plumbing Rough-in Inspection Partial Pass 9/5/2018 (12:30 - 2:30) 9/5/2018 09/05/2018
Corrections:


Miscellaneous/Other
Comment Only
09/05/2018
Underground Airtest on pantry

Plumbing Rough-in Inspection Not Ready 9/11/2018 (8:00 - 10:00) 9/11/2018 09/11/2018
Plumbing Rough-in Inspection Partial Pass 9/12/2018 (8:00 - 10:00) 9/12/2018 09/12/2018
Corrections:


Miscellaneous/Other
Comment Only
09/12/2018
Airtest on all including pantry. Visual in spection of pantry.

Plumbing Rough-in Inspection Not Ready 9/13/2018 (10:00 - 12:00) 9/13/2018 09/13/2018
Plumbing Rough-in Inspection Not Ready 9/17/2018 (12:30 - 2:30) 9/17/2018 09/17/2018
Plumbing Rough-in Inspection Partial Pass 9/18/2018 (10:00 - 12:00) 9/18/2018 09/18/2018
Plumbing Rough-in Inspection Partial Pass 9/21/2018 (2:30 - 3:30) 9/21/2018 09/21/2018
Corrections:


Miscellaneous/Other
Comment Only
09/21/2018
Airtest on all ug sanitary ok to cover

Plumbing Rough-in Inspection Partial Pass 1/2/2019 (8:00 - 10:00) 1/2/2019 (AM) 01/02/2019
Corrections:


Miscellaneous/Other
Comment Only
01/02/2019
Airtest on main gas line. Will be used for temporary heat. See connections with regulators and see venting.

Plumbing Rough-in Inspection Partial Pass 2/22/2019 (10:00 - 12:00) 2/22/2019 (AM) 02/22/2019
Corrections:


Miscellaneous/Other
Comment Only
02/22/2019
2nd floor waste and vent rough in completed. Future airtest.

Plumbing Rough-in Inspection Partial Pass 4/5/2019 (10:00 - 12:00) 4/5/2019 (AM) 04/05/2019
Corrections:


Miscellaneous/Other
Comment Only
04/05/2019
Airtest on 3 stakes. One additional stack to be tested.

Plumbing Rough-in Inspection Partial Pass 4/8/2019 (12:30 - 2:30) 4/8/2019 (PM) 04/08/2019
Corrections:


Miscellaneous/Other
Comment Only
04/08/2019
Airtest on last two waste and vent stacks. All ok to cover. Airtest on 5 storm leaders.

Plumbing Rough-in Inspection Partial Pass 4/25/2019 (8:00 - 10:00) 4/25/2019 (AM) 04/25/2019
Corrections:


Miscellaneous/Other
Comment Only
04/25/2019
Consultation. Spoke with plumbing foreman, Everett, about many damaged pipes from backing being installed. Also pipes are wedged in walls and have no movement for expansion and contraction or settling of the building. Spoke with superintendent Jerry and emphasized 1. that the backing in the walls shall be removed or replaced with a narrower backer board. 2.All insulation covering plumbing of kitchen sinks on 4th floor shall be removed. 3. Do not insulate or sheetrock until corrections have been made and plumbing is re-air tested. Good Air test on 2 rain water leaders and a roof top gas line.

Plumbing Rough-in Inspection Partial Pass 5/2/2019 (8:00 - 10:00) 5/2/2019 (AM) 05/02/2019
Corrections:


Miscellaneous/Other
Comment Only
05/02/2019
Entire building re-air tested in 4 sections after damaged pipe was replaced. All tests held. Approved.

Plumbing Rough-in Inspection Partial Pass 5/17/2019 (10:00 - 12:00) 5/17/2019 (AM) 05/17/2019
Corrections:


Miscellaneous/Other
Comment Only
05/17/2019

Miscellaneous/Other
Comment Only
05/20/2019
General contractor is sheet rocking over water pipe before it has been tested. Done at risk of general. Redundant valves on manifolds in hallway ceilings. Rebecca spoke with engineer about eliminating these valves as each fixture has a shut off valve. Engineer said he’d look into it. Engineer specified incompatible manifolds for piping material. Budget plumbing informed engineer and got no response. Budget plumbing is installing a compatible manifold with valves. Valves not needed at manifold. Rebecca requested that plumbing general Forman send engineer an R.F.I. To eliminate redundant valves. 1588 valves, with as many additional joints.

Miscellaneous/Other
Comment Only
05/20/2019
General contractor is sheet rocking over water pipe before it has been tested. Done at risk of general. Redundant valves on manifolds in hallway ceilings. Rebecca spoke with engineer about eliminating these valves as each fixture has a shut off valve. Engineer said he’d look into it. Engineer specified incompatible manifolds for piping material. Budget plumbing informed engineer and got no response. Budget plumbing is installing a compatible manifold with valves. Valves not needed at manifold. Rebecca requested that plumbing general Forman send engineer an R.F.I. To eliminate redundant valves. 1588 valves, with as many additional joints. 2nd floor rough in approved.

Miscellaneous/Other
Comment Only
05/20/2019
General contractor is sheet rocking over water pipe before it has been tested. Done at risk of general. Redundant valves on manifolds in hallway ceilings. Rebecca spoke with engineer about eliminating these valves as each fixture has a shut off valve. Engineer said he’d look into it. Engineer specified incompatible manifolds for piping material. Budget plumbing informed engineer and got no response. Budget plumbing is installing a compatible manifold with valves. Valves not needed at manifold. Rebecca requested that plumbing general Forman send engineer an R.F.I. To eliminate redundant valves. 1588 valves, with as many additional joints. 2nd floor rough in approved.

Miscellaneous/Other
Comment Only
05/21/2019
General contractor is sheet rocking over water pipe before it has been tested. Done at risk of general. Redundant valves on manifolds in hallway ceilings. Rebecca spoke with engineer about eliminating these valves as each fixture has a shut off valve. Engineer said he’d look into it. Engineer specified incompatible manifolds for piping material. Budget plumbing informed engineer and got no response. Budget plumbing is installing a compatible manifold with valves. Valves not needed at manifold. Rebecca requested that plumbing general Forman send engineer an R.F.I. To eliminate redundant valves. 1588 valves, with as many additional joints. 2nd floor rough in approved.

Plumbing Rough-in Inspection Partial Pass 9/14/2018 (12:30 - 2:30) 9/14/2018 08/08/2019
Plumbing Rough-in Inspection Passed 7/11/2019 (10:00 - 12:00) 7/11/2019 (AM) 08/09/2019
Corrections:


Miscellaneous/Other
Comment Only
07/11/2019
30/60 air test on 2 gas lines. Referred to Jesse for technical questions

Plumbing Rough-in Inspection Partial Pass 8/9/2019 (12:30 - 2:30) 8/9/2019 (PM) 08/09/2019
Plumbing Rough-in Inspection Partial Pass 8/12/2019 (12:30 - 2:30) 8/12/2019 (PM) 08/12/2019
Plumbing Rough-in Inspection Partial Pass 8/15/2019 (8:00 - 10:00) 8/15/2019 (AM) 08/15/2019
Corrections:


Miscellaneous/Other
Comment Only
08/15/2019
Visual on outside piping of grease interceptor

Plumbing Final Inspection Partial Pass 9/9/2019 (8:00 - 10:00) 9/9/2019 (AM) 09/09/2019
Plumbing Final Inspection Partial Pass 9/10/2019 (10:00 - 12:00) 9/10/2019 (AM) 09/10/2019
Plumbing Final Inspection Partial Pass 9/12/2019 (10:00 - 12:00) 9/12/2019 (AM) 09/12/2019
Plumbing Rough-in Inspection Partial Pass 10/15/2019 (8:00 - 10:00) 10/15/2019 (AM) 10/15/2019
Plumbing Final Inspection Partial Pass 12/4/2019 (8:00 - 10:00) 12/4/2019 (AM) 12/04/2019
Corrections:


Miscellaneous/Other
Comment Only
12/04/2019
Informational.

Plumbing Final Inspection Partial Pass 12/20/2019 (10:00 - 12:00) 12/20/2019 (AM) 12/20/2019
Plumbing Final Inspection Partial Pass 12/26/2019 (10:00 - 12:00) 12/26/2019 (AM) 12/26/2019
Plumbing Final Inspection Not Ready 12/27/2019 (10:00 - 12:00) 12/27/2019 (AM) 12/27/2019
Corrections:


Miscellaneous/Other
Comment Only
12/27/2019
Finish plumbing kitchen Set sinks in accessible rooms Test R.P.Z.

Plumbing Final Inspection Passed 12/31/2019 (12:30 - 2:30) 12/31/2019 (PM) 12/31/2019
Corrections:


Miscellaneous/Other
Comment Only
12/31/2019
Final approved pending installation of sinks in accessible rooms. Jon Aaron will inspect and sign off on the sinks.