PRPL201810679
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Underground Plumbing Inspection | Partial Pass | 10/12/2018 (12:30 - 2:30) | 10/12/2018 | 10/12/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2018
Visual on under ground sanitary main on
West side.
Ok to cover.
Future airtest.
|
||||
Underground Plumbing Inspection | Partial Pass | 10/16/2018 (10:00 - 12:00) | 10/16/2018 | 10/16/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/16/2018
Underground sanitary and storm visual-will see air later. Marked on plan what was inspected.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/18/2018 (12:30 - 2:30) | 10/18/2018 | 10/18/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2018
Visual inspection of underground sanitary sewer and risers.
Future airtest
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/19/2018 (12:30 - 2:30) | 10/19/2018 | 10/19/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/19/2018
Airtest on storm drain.
|
||||
Underground Plumbing Inspection | Partial Pass | 10/25/2018 (12:30 - 2:30) | 10/25/2018 | 10/25/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2018
Under ground Airtest. Marked on plan.
|
||||
Miscellaneous/Other
Outstanding
10/25/2018
|
||||
Underground Plumbing Inspection | Partial Pass | 10/31/2018 (10:00 - 12:00) | 10/31/2018 (AM) | 10/31/2018 |
Corrections:
Miscellaneous/Other
Comment Only
10/31/2018
Airtest on kitchen and bar underground ok to cover
All under ground tested.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/2/2019 (10:00 - 12:00) | 5/2/2019 (AM) | 05/02/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/02/2019
Visual of proposed wet venting of bathrooms- approved.
Approved for the use of expansion joints on storm drain and offset piping of 2 inch stacks.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/9/2019 (12:30 - 2:30) | 5/9/2019 (PM) | 05/09/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/09/2019
Consultation: discharge location of mechanical condensate. Rebecca contacted Eric Schoon in the water department. Eric referred Rebecca to the city storm engineering department.
Rebecca will be in contact with Hardy
After consultation with engineering.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/3/2019 (Afternoon) | 6/3/2019 (PM) | 06/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/04/2019
Air tests on 12 roof drains and overflows
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/3/2019 (12:30 - 2:30) | 7/3/2019 (PM) | 07/03/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/03/2019
Airtest on 8 stacks, ok to cover.
|
||||
Plumbing Rough-in Inspection | Passed | 7/9/2019 (12:30 - 2:30) | 7/9/2019 (PM) | 07/09/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/09/2019
Air test on 1/4 of building.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/10/2019 (12:30 - 2:30) | 7/10/2019 (PM) | 07/10/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/10/2019
Air tests on 1/4 of building. One dropped, will check test ball and retest.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/11/2019 (12:30 - 2:30) | 7/11/2019 (PM) | 07/11/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/11/2019
2nd floor walk through
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/12/2019 (8:00 - 10:00) | 7/12/2019 (AM) | 07/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2019
Air tests complete
|
||||
Miscellaneous/Other
Comment Only
07/12/2019
Air tests complete
|
||||
Plumbing Rough-in Inspection | Passed | 7/8/2019 (10:00 - 12:00) | 7/8/2019 (AM) | 07/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/08/2019
Visual walk through of 6th floor, 3/4 of 5th floor waste and vent. Ok to cover after testing completed.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/8/2019 (12:30 - 2:30) | 8/8/2019 (PM) | 08/08/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/08/2019
Air test on 2-3” roof drains
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/9/2019 (12:30 - 2:30) | 8/9/2019 (PM) | 08/09/2019 |
Plumbing Rough-in Inspection | Partial Pass | 8/26/2019 (10:00 - 12:00) | 8/26/2019 (AM) | 08/26/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/26/2019
Air test on public bathrooms and resident laundry
Manometer test on laundry
Air test on 4 units
Visual on kitchen, ok to cover-future air test on kitchen
Jesse took Air test on kitchen
Waiting to complete piping over the pool.
|
||||
Plumbing Rough-in Inspection | Passed | 9/24/2019 (10:00 - 12:00) | 10/1/2019 (AM) | 10/01/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/01/2019
Air test on last 4 stacks. Sump with p-trap for pool drains
P-trap for emptying pool
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/15/2019 (8:00 - 10:00) | 10/15/2019 (AM) | 10/15/2019 |
Plumbing Rough-in Inspection | Partial Pass | 10/16/2019 (PM) | 10/15/2019 | |
Plumbing Rough-in Inspection | Partial Pass | 10/16/2019 (PM) | 10/15/2019 | |
Plumbing Final Inspection | Partial Pass | 10/17/2019 (8:00 - 10:00) | 10/17/2019 (AM) | 10/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/17/2019
Sink in 542, 531, 537, 546,542, 536, 545,
Leak in 504
Waters off in 501 wing
|
||||
Plumbing Final Inspection | Partial Pass | 10/28/2019 (8:00 - 10:00) | 10/28/2019 (AM) | 10/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/28/2019
Manometer on kitchen
walk through on 5th floor
|
||||
Miscellaneous/Other
Comment Only
10/28/2019
Manometer on kitchen
walk through on 5th floor
|
||||
Plumbing Final Inspection | Partial Pass | 11/1/2019 (8:00 - 10:00) | 11/1/2019 (AM) | 11/01/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2019
4th floor walk through
|
||||
Plumbing Final Inspection | Partial Pass | 11/12/2019 (12:30 - 2:30) | 11/12/2019 (PM) | 11/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/12/2019
Kitchen island vent
3rd floor walk through
|
||||
Plumbing Final Inspection | Partial Pass | 12/18/2019 (10:00 - 12:00) | 12/18/2019 (AM) | 12/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/18/2019
|
||||
Miscellaneous/Other
Comment Only
12/18/2019
Replace toilet tank in employee bathroom-right hand flush
Pipe 2 traps in kitchen
Pipe ice makers
Caulk mop sinks
Set individual sinks not set yet
Set 8 lavatories
|
||||
Miscellaneous/Other
Comment Only
12/18/2019
Replace toilet tank in employee bathroom-right hand flush
Pipe 2 traps in kitchen
Pipe ice makers
Caulk mop sinks
Set individual sinks not set yet
Set 8 lavatories
|
||||
Plumbing Final Inspection | Partial Pass | 1/2/2020 (10:00 - 12:00) | 1/2/2020 (AM) | 01/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/02/2020
Manometer test on south side of building
Gas installation for dryers ok
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/7/2020 (10:00 - 12:00) | 1/7/2020 (AM) | 01/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/07/2020
Visual rough in on the bar
Kitchen completed
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/14/2020 (10:00 - 12:00) | 1/14/2020 (AM) | 01/14/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/14/2020
Manometer on north side of building
Visual on bar.
|
||||
Plumbing Rough-in Inspection | Passed | 1/15/2020 (10:00 - 12:00) | 1/15/2020 (AM) | 01/15/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/15/2020
Final manometer tests.
|