Permit Application Status

PRPL201811701


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201811701
Plumbing
Finaled
THERMO KING CORPORATION
Alteration/Remodel
Demo existing restrooms. Provide all plumbing for new restrooms. (6) water closets, (3) urinals, (8) lav sinks, (2) showers, (1) laundry tub, (1) electric water heater, and (2) floor drains.
10/01/2018
10/01/2018
07/09/2019
01/10/2019

Locations

Permits

Permit Number: PRPL201811701

Plumbing
Finaled
10/01/2018
07/09/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Not Ready 11/14/2018 (12:30 - 2:30) 11/14/2018 (PM) 11/14/2018
Corrections:


Miscellaneous/Other
Comment Only
11/14/2018
Unable to reach plumber while at location. Voice mail was not set up. Unable to leave a message. Please reschedule.

Plumbing Rough-in Inspection Partial Pass 11/15/2018 (12:30 - 2:30) 11/15/2018 (PM) 11/15/2018
Corrections:


Miscellaneous/Other
Comment Only
11/15/2018
Airtest on underground ok to cover.

Plumbing Rough-in Inspection Partial Pass 11/26/2018 (8:00 - 10:00) 11/26/2018 (AM) 11/26/2018
Corrections:


Miscellaneous/Other
Resolved
11/26/2018
Shower pan inspection approved.

Plumbing Rough-in Inspection Passed 11/27/2018 (12:30 - 2:30) 11/27/2018 (PM) 11/27/2018
Corrections:


Miscellaneous/Other
Comment Only
11/27/2018
Rough in airtest on all waste and vent Ok to cover all when lav water lines are completed.

Plumbing Final Inspection Passed 1/10/2019 (10:00 - 12:00) 1/10/2019 (AM) 01/10/2019
Corrections:


Miscellaneous/Other
Comment Only
01/10/2019
Manometer test Repiping of sewage ejector