PRPL201811929
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Rough-in Inspection | Passed w/ Conditions | 11/16/2018 (8:00 - 10:00) | 11/16/2018 (AM) | 11/16/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/16/2018
Finish water piping in wall.
|
||||
| Plumbing Final Inspection | Partial Pass | 12/13/2018 (12:30 - 2:30) | 12/13/2018 (PM) | 12/13/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/13/2018
Partial final
|
||||
| Plumbing Final Inspection | Passed w/ Conditions | 12/17/2018 (12:30 - 2:30) | 12/17/2018 (PM) | 12/17/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/17/2018
Repipe condensate lines and send photo when completed.
|
||||