PRPL201813420
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Final Inspection | Pending | |||
Plumbing Rough-in Inspection | Passed | 11/1/2018 (8:00 - 10:00) | 11/1/2018 (AM) | 11/01/2018 |
Corrections:
Miscellaneous/Other
Resolved
11/01/2018
No one on site to verify location of bottle filler.
|