PRPL201814275
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 12/5/2018 (10:00 - 12:00) | 12/5/2018 (AM) | 12/05/2018 |
Plumbing Final Inspection | Passed | 2/14/2019 (12:30 - 2:30) | 2/14/2019 (PM) | 02/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/14/2019
No stand pipe installed. As per plumbing Rough-in inspector allowed the piping from pan to hook up to the sink tail piece.
All plumbing installations are approved.
|