PRPL201814954
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Plumbing Rough-in Inspection | Pending | |||
| Plumbing Final Inspection | Pending | |||
| Plumbing Rough-in Inspection | Partial Pass | 12/13/2018 (12:30 - 2:30) | 12/13/2018 (PM) | 12/13/2018 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/13/2018
Visual on under ground elevator pit drain and sump. South side.
|
||||
| Plumbing Rough-in Inspection | Partial Pass | 1/16/2019 (12:30 - 2:30) | 1/16/2019 (PM) | 01/16/2019 |
|
Corrections:
Miscellaneous/Other
Comment Only
01/16/2019
Elevator pit tank
|
||||