Permit Application Status

PRPL201900367


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201900367
Plumbing
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Remodel of restrooms at Nordstrom MOA - replacement of fixtures. Valuation increased 28,600 due to addition of cafe etc Morehouse Michael 01/18/2019 8:11 AM
01/11/2019
01/28/2019
05/18/2020
11/20/2019

Locations

Permits

Permit Number: PRPL201900367

Plumbing
Finaled
01/28/2019
05/18/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 2/4/2019 (10:00 - 12:00) 2/4/2019 (AM) 02/04/2019
Rebecca is out. NelsonThorpe Sarah 01/29/2019 12:09 PM
Corrections:


Miscellaneous/Other
Comment Only
02/04/2019
Inwall RI ok cafe bathrooms 3rd floor

Plumbing Rough-in Inspection Partial Pass 2/26/2019 (8:00 - 10:00) 2/26/2019 (AM) 02/26/2019
Corrections:


Miscellaneous/Other
Comment Only
02/26/2019
Final on employee kitchen

Plumbing Final Inspection Partial Pass 3/13/2019 (8:00 - 10:00) 3/13/2019 (AM) 03/13/2019
Corrections:


Miscellaneous/Other
Comment Only
03/13/2019
Final on 2 accessible bathrooms

Plumbing Rough-in Inspection Partial Pass 4/9/2019 (8:00 - 10:00) 4/9/2019 (AM) 04/09/2019
Corrections:


All corrections have been made.
Comment Only
04/09/2019
All corrections have been made. 2nd phase women’s restroom rough in. New sink configuration, new closet flanges, floor drain and mothers sink.

Plumbing Rough-in Inspection Partial Pass 5/29/2019 (8:00 - 10:00) 5/29/2019 (AM) 05/29/2019
Corrections:


Miscellaneous/Other
Comment Only
05/29/2019
Visual final on women’s restrooms.

Plumbing Rough-in Inspection Partial Pass 6/28/2019 6/28/2019 (AM) 06/28/2019
Corrections:


Miscellaneous/Other
Comment Only
06/28/2019
Visual rough in on men’s bathroom It’s floor

Plumbing Final Inspection Partial Pass 8/6/2019 (8:00 - 10:00) 8/6/2019 (AM) 08/06/2019
Corrections:


Miscellaneous/Other
Comment Only
08/06/2019
Partial final Men’s restroom 1st floor

Plumbing Rough-in Inspection Passed 8/13/2019 (12:30 - 2:30) 8/13/2019 (PM) 08/13/2019
Corrections:


Miscellaneous/Other
Comment Only
08/13/2019
Kitchen RI ok to cover when waters are completed.

Plumbing Final Inspection Partial Pass 10/24/2019 (10:00 - 12:00) 10/24/2019 (AM) 10/24/2019
Corrections:


Miscellaneous/Other
Comment Only
10/24/2019
Kitchen final 2nd floor bathroom final.

Plumbing Final Inspection Passed 11/20/2019
Corrections:


Miscellaneous/Other
Comment Only
11/20/2019
All work completed, permit final approved