PRPL201900367
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 2/4/2019 (10:00 - 12:00) | 2/4/2019 (AM) | 02/04/2019 |
Rebecca is out. NelsonThorpe Sarah 01/29/2019 12:09 PM | ||||
Corrections:
Miscellaneous/Other
Comment Only
02/04/2019
Inwall RI ok cafe bathrooms 3rd floor
|
||||
Plumbing Rough-in Inspection | Partial Pass | 2/26/2019 (8:00 - 10:00) | 2/26/2019 (AM) | 02/26/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/26/2019
Final on employee kitchen
|
||||
Plumbing Final Inspection | Partial Pass | 3/13/2019 (8:00 - 10:00) | 3/13/2019 (AM) | 03/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/13/2019
Final on 2 accessible bathrooms
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/9/2019 (8:00 - 10:00) | 4/9/2019 (AM) | 04/09/2019 |
Corrections:
All corrections have been made.
Comment Only
04/09/2019
All corrections have been made.
2nd phase women’s restroom rough in. New sink configuration, new closet flanges, floor drain and mothers sink.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/29/2019 (8:00 - 10:00) | 5/29/2019 (AM) | 05/29/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/29/2019
Visual final on women’s restrooms.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/28/2019 | 6/28/2019 (AM) | 06/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/28/2019
Visual rough in on men’s bathroom
It’s floor
|
||||
Plumbing Final Inspection | Partial Pass | 8/6/2019 (8:00 - 10:00) | 8/6/2019 (AM) | 08/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/06/2019
Partial final
Men’s restroom 1st floor
|
||||
Plumbing Rough-in Inspection | Passed | 8/13/2019 (12:30 - 2:30) | 8/13/2019 (PM) | 08/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/13/2019
Kitchen RI ok to cover when waters are completed.
|
||||
Plumbing Final Inspection | Partial Pass | 10/24/2019 (10:00 - 12:00) | 10/24/2019 (AM) | 10/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/24/2019
Kitchen final
2nd floor bathroom final.
|
||||
Plumbing Final Inspection | Passed | 11/20/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/20/2019
All work completed, permit final approved
|