PRPL201900859
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 2/1/2019 (12:30 - 2:30) | 2/1/2019 (PM) | 02/01/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/01/2019
10th floor plumbing completed. Will circle floor and check that shower trim is sealed.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 2/6/2019 (8:00 - 10:00) | 2/6/2019 (AM) | 02/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
02/06/2019
2nd floor final
|
||||
Plumbing Rough-in Inspection | Partial Pass | 3/5/2019 (8:00 - 10:00) | 3/5/2019 (AM) | 03/05/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/05/2019
9th floor final
|
||||
Plumbing Rough-in Inspection | Partial Pass | 3/12/2019 (8:00 - 10:00) | 3/12/2019 (AM) | 03/12/2019 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2019
8th floor final
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/2/2019 (8:00 - 10:00) | 4/2/2019 (AM) | 04/02/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/02/2019
7th floor final. Corner rooms not completed. Vanities missing in 712, 709, 708, 707.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/10/2019 (8:00 - 10:00) | 4/10/2019 (AM) | 04/10/2019 |
Corrections:
All corrections have been made.
Comment Only
04/10/2019
All corrections have been made.
4-10-2019. 6th floor final. 4 toilets in disrepair. Missing stoppers in tub drains.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 4/30/2019 | 4/30/2019 (AM) | 04/30/2019 |
Corrections:
Miscellaneous/Other
Comment Only
04/30/2019
Trap and faucet in 510
Tank cover in 512, 528
Tub stopper in 518, 524, 530, 536
Toilet in 526
Waste and overflow trim in 527, 529(broken), 530
Tub spout 536
Caulk tub spouts and shower valve trim
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/6/2019 (10:00 - 12:00) | 5/6/2019 (AM) | 05/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2019
Rough-in visual on ADA rooms 715, 815, 915, 1015 Waste and vent ok one open end vent in Chase in 715. Waters not completed. Firecualk holes used for stacks on remodel.
|
||||
Plumbing Final Inspection | Partial Pass | 5/7/2019 (10:00 - 12:00) | 5/7/2019 (AM) | 05/07/2019 |
Corrections:
Miscellaneous/Other
Comment Only
05/07/2019
Tub stoppers in 401, 407, 412, 420, 423
Missing tank in 401
Sink stopper in 413
Broken waste and overflow faceplate or missing in 412???? and 433
Valve leaks in 434????
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/22/2019 (8:00 - 10:00) | 5/22/2019 (AM) | 05/22/2019 |
Corrections:
Miscellaneous/Other
Carried Forward
05/22/2019
|
||||
Miscellaneous/Other
Outstanding
05/22/2019
1.Turn on all toilets and check for leaks
2. Finish sealing base of toilets
3. Toilet tank covers missing or broken in: 306, 317, 318, 331
4. 305 plugged coffee sink
5. 308 broken tub over flow cover
6. 319 missing tub overflow cover plate
7. 323 tub stopper broken internally
8. 324 tub stopper missing
9. 336 waste and overflow plate- adjust to cover hole and tighten
10. Request that cleaners replace pop up drains on vanities and screw down all the way
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/14/2019 (8:00 - 10:00) | 6/14/2019 (AM) | 06/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2019
install shower valves,
complete piping and fire caulking in 315
|
||||
Plumbing Final Inspection | Partial Pass | 7/17/2019 (12:30 - 2:30) | 7/17/2019 (PM) | 07/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/17/2019
Final on ADA rooms 315-1015
|
||||
Plumbing Rough-in Inspection | Passed | 7/22/2019 (10:00 - 12:00) | 7/22/2019 (AM) | 07/22/2019 |
Plumbing Final Inspection | Passed | 9/3/2019 (8:00 - 10:00) | 9/3/2019 (AM) | 09/02/2019 |