Permit Application Status

PRPL201903002


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201903002
Plumbing
Finaled
DOLAN SEXTON & HEIM RLTY
Alteration/Repair/Replace
Break room sink addition in suite 115. Southtown Office Park Ste 115
04/04/2019
04/05/2019
11/24/2019
05/28/2019

Locations

Permits

Permit Number: PRPL201903002

Plumbing
Finaled
04/05/2019
11/24/2019

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Passed 4/10/2019 (12:30 - 2:30) 4/10/2019 (PM) 04/10/2019
Plumbing Final Inspection Passed 5/28/2019 (10:00 - 12:00) 5/28/2019 (AM) 05/28/2019