Permit Application Status

PRPL201903601


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL201903601
Plumbing
Finaled
THE BEDROOM INC
Other
Roof Drains, Bathrooms - New Store
04/19/2019
06/04/2019
09/22/2020
03/26/2020

Locations

Permits

Permit Number: PRPL201903601

Plumbing
Finaled

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 6/24/2019 (2:30 - 3:30) 6/24/2019 (PM) 06/24/2019
Miscellaneous/Other
Comment Only
06/24/2019
Air test on 180 feet for elevator pit drain. Buried, saw photo

Plumbing Rough-in Inspection Partial Pass 6/25/2019 (2:30 - 3:30) 6/25/2019 (PM) 06/25/2019
Miscellaneous/Other
Comment Only
06/25/2019
189 feet of pipe laid. Buried, unable to inspect. Finish elevator sump drain, put on Airtest and call for inspection.

Plumbing Rough-in Inspection Not Ready 6/26/2019 (2:30 - 3:30) 6/26/2019 (PM) 06/26/2019
Plumbing Rough-in Inspection Not Ready 6/27/2019 (2:30 - 3:30) 6/27/2019 (PM) 06/27/2019
Miscellaneous/Other
Comment Only
06/27/2019
Rained out

Plumbing Rough-in Inspection Partial Pass 9/16/2019 (10:00 - 12:00) 9/16/2019 (AM) 09/16/2019
Miscellaneous/Other
Comment Only
09/16/2019
Air test on under ground for break room sink

Plumbing Rough-in Inspection Partial Pass 9/19/2019 (8:00 - 10:00) 9/19/2019 (AM) 09/19/2019
Miscellaneous/Other
Comment Only
09/19/2019
Rough in air test on under ground for bathrooms, ok to backfill

Plumbing Rough-in Inspection Partial Pass 10/7/2019 (12:30 - 2:30) 10/7/2019 (PM) 10/07/2019
Plumbing Rough-in Inspection Partial Pass 10/8/2019 (12:30 - 2:30) 10/8/2019 (PM) 10/08/2019
Plumbing Rough-in Inspection Partial Pass 10/9/2019 (12:30 - 2:30) 10/9/2019 (PM) 10/09/2019
Plumbing Rough-in Inspection Not Ready 10/10/2019 (12:30 - 2:30) 10/10/2019 (PM) 10/10/2019
Plumbing Rough-in Inspection Partial Pass 10/14/2019 (12:30 - 2:30) 10/14/2019 (PM) 10/14/2019
Miscellaneous/Other
Comment Only
10/14/2019
Air test on under ground storm

Plumbing Rough-in Inspection Partial Pass 10/15/2019 (12:30 - 2:30) 10/15/2019 (PM) 10/15/2019
Plumbing Rough-in Inspection Partial Pass 10/16/2019 (12:30 - 2:30) 10/16/2019 (PM) 10/16/2019
Miscellaneous/Other
Comment Only
10/16/2019
Ugat

Plumbing Rough-in Inspection Partial Pass 10/17/2019 (12:30 - 2:30) 10/17/2019 (PM) 10/17/2019
Plumbing Rough-in Inspection Partial Pass 12/9/2019 (12:30 - 2:30) 12/9/2019 (PM) 12/09/2019
Miscellaneous/Other
Comment Only
12/09/2019
West side of building air tested.

Plumbing Rough-in Inspection Partial Pass 12/10/2019 (10:00 - 12:00) 12/10/2019 (AM) 12/10/2019
Miscellaneous/Other
Comment Only
12/10/2019
Air test on 2 roof drain rain leaders

Plumbing Rough-in Inspection Partial Pass 12/18/2019 (12:30 - 2:30) 12/18/2019 (PM) 12/18/2019
Miscellaneous/Other
Comment Only
12/18/2019
Airtest on 4 roof drains And upper level bathroom

Plumbing Rough-in Inspection Partial Pass 12/27/2019 (12:30 - 2:30) 12/27/2019 (PM) 12/27/2019
Miscellaneous/Other
Comment Only
12/27/2019
Air test on 4 rain leaders on the east side

Plumbing Rough-in Inspection Passed 1/14/2020 (12:30 - 2:30) 1/14/2020 (PM) 01/14/2020
Miscellaneous/Other
Comment Only
01/14/2020
Air test on 3 over flows and 4 bathrooms

Plumbing Final Inspection Partial Pass 3/2/2020 (10:00 - 12:00) 3/2/2020 (AM) 03/02/2020
Miscellaneous/Other
Comment Only
03/02/2020
Manometer tests on 2 bathrooms

Plumbing Final Inspection Passed 3/26/2020 (10:00 - 12:00) 3/26/2020 (AM) 03/26/2020