PRPL201908610
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 8/28/2019 (8:00 - 10:00) | 8/28/2019 (AM) | 08/28/2019 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2019
In wall sinks ok to cover
Use double fixture fittings on back to back sinks. Ok to stack tees
3”” main vent ok
Valve 2”” water main in tenant space
|
||||
Plumbing Rough-in Inspection | Passed | 9/6/2019 (8:00 - 10:00) | 9/6/2019 (AM) | 09/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/06/2019
Air test on all
|
||||
Plumbing Final Inspection | Passed | 10/29/2019 (8:00 - 10:00) | 10/29/2019 (AM) | 10/29/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/29/2019
Manometer test
Turn on water, check for leaks
Set one toilet
|