PRPL201908829
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 9/4/2019 (12:30 - 2:30) | 9/4/2019 (PM) | 09/04/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/04/2019
Air test on under ground
Ok to backfill
|
||||
Plumbing Rough-in Inspection | Passed | 9/20/2019 (2:30 - 3:30) | 9/20/2019 (PM) | 09/20/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/20/2019
Airtest on all waste and vent and waters
|
||||
Plumbing Rough-in Inspection | Passed | 10/18/2019 (2:30 - 3:30) | 10/18/2019 (PM) | 10/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2019
Shower pan inspections
|
||||
Plumbing Final Inspection | Passed | 11/14/2019 (12:30 - 2:30) | 11/14/2019 (PM) | 11/14/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/14/2019
Manometer holds (2 systems) fixtures set and sealed. 30# airtest gasline for water heaters. Final
|