PRPL201914432
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 5/5/2020 (12:30 - 2:30) | 5/5/2020 (PM) | 05/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/05/2020
Visual on under ground for flammable waste tank and trench drains. Future air test
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/6/2020 (12:30 - 2:30) | 5/6/2020 (PM) | 05/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2020
Air test on under ground sanitary line and flammable line on the northeast side of building
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/7/2020 (12:30 - 2:30) | 5/7/2020 (PM) | 05/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/07/2020
Air tests on underground flammable waste and sanitary sewers next north side
|
||||
Plumbing Rough-in Inspection | Partial Pass | 5/12/2020 (8:00 - 10:00) | 5/12/2020 (AM) | 05/12/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2020
Air test on all under ground waste, vent and flammable.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 6/30/2020 (10:00 - 12:00) | 6/30/2020 (AM) | 06/30/2020 |
Corrections:
Miscellaneous/Other
Comment Only
06/30/2020
In wall air test sanitary 5#-“A” wing to 2 hour wall
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/1/2020 (10:00 - 12:00) | 7/1/2020 (AM) | 07/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/01/2020
3# air on storm primary and overflow area A to fire wall
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/2/2020 (10:00 - 12:00) | 7/2/2020 (AM) | 07/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/02/2020
Visual 4th floor southwest wing ok to cover-showers not se waiting for gyp
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/6/2020 (8:00 - 10:00) | 7/6/2020 (AM) | 07/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/06/2020
301, 302 and 303 have no cards. Visual rough in approved.
2nd floor has no cards. Signed door jams
Water mains and manifolds look good on 3rd and 2nd.
Shower bases and valves not in on 3rd or 2nd
Nail plates 2nd floor
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/7/2020 (10:00 - 12:00) | 7/7/2020 (AM) | 07/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/07/2020
Visual center 4th floor 3rd floor partial visual
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/8/2020 (10:00 - 12:00) | 7/8/2020 (AM) | 07/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/08/2020
Walk through remainder of 3rd and 2nd floors. phase 1 south side
|
||||
Miscellaneous/Other
Comment Only
07/08/2020
Walk through remainder of 3rd and 2nd floors. phase 1 south side
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/9/2020 (10:00 - 12:00) | 7/9/2020 (AM) | 07/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/09/2020
1st floor rough in
4th floor showers
|
||||
Plumbing Rough-in Inspection | Partial Pass | 7/16/2020 (10:00 - 12:00) | 7/16/2020 (AM) | 07/16/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/16/2020
Walk through of 3,2,1, after showers installed
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/5/2020 (10:00 - 12:00) | 8/5/2020 (AM) | 08/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2020
North side 4th for walk through
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/5/2020 (10:00 - 12:00) | 8/5/2020 (AM) | 08/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2020
North side 3rd floor walk through
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/5/2020 (10:00 - 12:00) | 8/5/2020 (AM) | 08/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2020
North side 2nd floor walk through
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/5/2020 (10:00 - 12:00) | 8/5/2020 (AM) | 08/05/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2020
3# air test on one set of 8” storm primary drain and over flow
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/10/2020 (12:30 - 2:30) | 8/10/2020 (PM) | 08/10/2020 |
Plumbing Rough-in Inspection | Partial Pass | 8/10/2020 (12:30 - 2:30) | 8/10/2020 (PM) | 08/10/2020 |
Plumbing Rough-in Inspection | Partial Pass | 8/10/2020 (12:30 - 2:30) | 8/10/2020 (PM) | 08/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/10/2020
Air test on one roof drain over flow
Air tests on one wing
Walk through on 1st floor
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/10/2020 (12:30 - 2:30) | 8/10/2020 (PM) | 08/10/2020 |
Plumbing Rough-in Inspection | Partial Pass | 8/17/2020 (8:00 - 10:00) | 8/17/2020 (AM) | 08/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/17/2020
Air on commercial kitchen.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/19/2020 (8:00 - 10:00) | 8/19/2020 (AM) | 08/19/2020 |
Plumbing Rough-in Inspection | Partial Pass | 9/16/2020 (AM) | 09/16/2020 | |
Plumbing Rough-in Inspection | Passed | 11/18/2020 (8:00 - 10:00) | 11/18/2020 (AM) | 11/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/18/2020
Test RPZ’s
Cast iron blind plugs on rain leaders where they leave the building instead of rubber caps.
Garage final approved with these conditions.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 11/19/2020 (8:00 - 10:00) | 11/19/2020 (AM) | 11/19/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2020
Sprayer hose on kitchen sinks doesn’t retract in 401, 402, 404, 406.
Dishwasher loose in 416.
Show documentation of back flow protection on hand held showers.
|
||||
Plumbing Final Inspection | Partial Pass | 12/16/2020 (12:30 - 2:30) | 12/16/2020 (PM) | 12/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2020
Final walk through of 2nd and 3rd floors
|
||||
Plumbing Final Inspection | Partial Pass | 12/17/2020 (12:30 - 2:30) | 12/17/2020 (PM) | 12/17/2020 |
Plumbing Final Inspection | Partial Pass | 12/18/2020 (10:00 - 12:00) | 12/18/2020 (AM) | 12/18/2020 |
Plumbing Final Inspection | Partial Pass | 12/18/2020 (10:00 - 12:00) | 12/18/2020 (AM) | 12/18/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
12/22/2020
1st floor walk through
Unit
131 lav pop up too hard to close for old hands
|
||||
Plumbing Final Inspection | Partial Pass | 12/21/2020 (10:00 - 12:00) | 12/21/2020 (AM) | 12/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2020
Public bathroom 175 - adjust flush valve
103 - pop up doesn’t close
Manometer test completed
|
||||
Plumbing Final Inspection | Partial Pass | 12/22/2020 (10:00 - 12:00) | 12/22/2020 (AM) | 12/22/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/22/2020
Turn on water to toilet tank in 427
|
||||
Plumbing Final Inspection | Passed | 2/9/2021 (10:00 - 12:00) | 2/9/2021 (AM) | 02/09/2021 |
Corrections:
Miscellaneous/Other
Outstanding
12/22/2020
1st floor walk through
Unit
131 lav pop up too hard to close for old hands
|