Permit Application Status

PRPL202000721


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202000721
Plumbing
Finaled
THE LUTHER COMPANY LLLP
Alteration/Repair/Replace
NEW car dealership w/service drive, service area, offices, showroom, car was and new car delivery. The Office, service area and new car delivery is air conditioned. The service drive area and new car delivery have a carbon monoxide exhaust system. There is one (1) VAV rooftop unit serving the office area on both 1st and 2nd level. The parts area, car lift, service area and new car delivery are served by separate constant volume rooftop units.
01/24/2020
02/12/2020
08/09/2021
02/19/2021

Locations

Permits

Permit Number: PRPL202000721

Plumbing
Finaled
02/12/2020
08/09/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 5/15/2020 (8:00 - 10:00) 5/15/2020 (AM) 05/15/2020
Corrections:


Miscellaneous/Other
Comment Only
05/15/2020
Pictures of 6” drain from elevator and connection to sump tank

Plumbing Rough-in Inspection Partial Pass 5/21/2020 (10:00 - 12:00) 5/21/2020 (AM) 05/21/2020
Corrections:


Miscellaneous/Other
Comment Only
05/21/2020
Air test on flammable waste trap piping

Plumbing Rough-in Inspection Partial Pass 6/2/2020 (10:00 - 12:00) 6/2/2020 (AM) 06/02/2020
Corrections:


Miscellaneous/Other
Comment Only
06/02/2020
5# flam and sanitary deep shop area

Plumbing Rough-in Inspection Partial Pass 6/4/2020 (10:00 - 12:00) 6/4/2020 (AM) 06/04/2020
Corrections:


Miscellaneous/Other
Comment Only
06/04/2020
Manometer test on flammable waste tank. ok to bury two offsets to floor drains air test on Flammable waste under ground. ok to cover Air test on sanitary sewer, ok to cover

Plumbing Rough-in Inspection Partial Pass 6/17/2020 (10:00 - 12:00) 6/17/2020 (AM) 06/17/2020
Corrections:


Miscellaneous/Other
Comment Only
06/17/2020
Air test on flammable waste for trench drains. Ok to backfill

Plumbing Rough-in Inspection Partial Pass 6/19/2020 (10:00 - 12:00) 6/19/2020 (AM) 06/19/2020
Plumbing Rough-in Inspection Partial Pass 6/24/2020 (10:00 - 12:00) 6/24/2020 (AM) 06/24/2020
Corrections:


Miscellaneous/Other
Comment Only
06/24/2020
Air test on flammable waste

Plumbing Rough-in Inspection Partial Pass 6/26/2020 (8:00 - 10:00) 6/26/2020 (AM) 06/26/2020
Corrections:


Miscellaneous/Other
Comment Only
06/26/2020
Air test on all flammable waste

Plumbing Rough-in Inspection Not Ready 7/7/2020 (8:00 - 10:00) 7/7/2020 (AM) 07/07/2020
Plumbing Rough-in Inspection Partial Pass 7/8/2020 (8:00 - 10:00) 7/8/2020 (AM) 07/08/2020
Corrections:


Miscellaneous/Other
Comment Only
07/08/2020
Under ground 12” storm. South side air test Sanitary under ground and flammable waste under ground air tested in shop area , car delivery and car wash, equipment room and trash room

Plumbing Rough-in Inspection Partial Pass 7/13/2020 (10:00 - 12:00) 7/13/2020 (AM) 07/13/2020
Corrections:


Miscellaneous/Other
Comment Only
07/13/2020
Air test on underground sanitary for 1st floor bathrooms and mothers room sink. Visual on 3 trench drains. Will see installation of interior trench drains.

Plumbing Rough-in Inspection Partial Pass 7/31/2020 (12:30 - 2:30) 7/31/2020 (PM) 07/31/2020
Corrections:


Miscellaneous/Other
Comment Only
07/31/2020
3# air 2nd floor primary and secondary 5# air all second floor waste and vent except men’s locker and mop sink

Plumbing Rough-in Inspection Partial Pass 8/20/2020 (10:00 - 12:00) 8/20/2020 (AM) 08/20/2020
Corrections:


Minimum Clearance
Comment Only
08/20/2020
air Test on upper level plumbing

Plumbing Rough-in Inspection Partial Pass 9/9/2020 (10:00 - 12:00) 9/9/2020 (AM) 09/09/2020
Corrections:


Miscellaneous/Other
Comment Only
09/09/2020
Additional storm drain on 1st level tested live. 2 Bathroom groups, drinking fountain, mop sink - all waste, vent and water air tested ok to cover.

Plumbing Rough-in Inspection Partial Pass 9/17/2020 (10:00 - 12:00) 9/17/2020 (AM) 09/17/2020
Corrections:


Miscellaneous/Other
Comment Only
09/17/2020
Air test on main roof drains and overflows Air test on men’s/women’s upper floor bathrooms and shower rooms.

Plumbing Rough-in Inspection Partial Pass 10/13/2020 (10:00 - 12:00) 10/13/2020 (AM) 10/13/2020
Corrections:


Miscellaneous/Other
Comment Only
10/13/2020
Air test on upper level and venting

Plumbing Rough-in Inspection Partial Pass 10/29/2020 (10:00 - 12:00) 10/29/2020 (AM) 10/29/2020
Corrections:


Miscellaneous/Other
Comment Only
10/29/2020
Air test on Primary and secondary roof drains over entry way

Plumbing Final Inspection Partial Pass 1/22/2021 (10:00 - 12:00) 1/22/2021 (AM) 01/22/2021
Corrections:


Miscellaneous/Other
Comment Only
01/22/2021
Manometer tests. Walk through. Two sinks to install Passed with conditions to install 2 sinks RLA will re-inspect

Plumbing Final Inspection Passed 2/10/2021 (12:30 - 2:30) 2/10/2021 (PM) 02/10/2021