Permit Application Status

PRPL202006692


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPL202006692
Plumbing
Finaled
AMIRA INSPIRE BLOOMINGTON LLC
Alteration/Repair/Replace
Complete plumbing system in new 133 unit apartment building.
06/25/2020
10/01/2020
05/30/2022
12/01/2021

Locations

Permits

Permit Number: PRPL202006692

Plumbing
Finaled
10/01/2020
05/30/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 12/15/2020 (2:30 - 3:30) 12/15/2020 (PM) 12/16/2020
Corrections:


Miscellaneous/Other
Comment Only
12/16/2020
Air test on under ground sanitary. Air test On under ground flammable waste.

Miscellaneous/Other
Comment Only
12/16/2020
Air test on under ground sanitary. Air test On under ground flammable waste.

Plumbing Rough-in Inspection Partial Pass 12/16/2020 (12:30 - 2:30) 12/16/2020 (PM) 12/17/2020
Corrections:


Miscellaneous/Other
Comment Only
12/17/2020
Air test on under ground sanitary and flammable waste Manometer test on flammable waste tank

Plumbing Rough-in Inspection Partial Pass 12/17/2020 (8:00 - 10:00) 12/17/2020 (AM) 12/17/2020
Corrections:


Miscellaneous/Other
Comment Only
12/17/2020
Inspection of setting of 2 storm water tanks

Plumbing Rough-in Inspection Partial Pass 12/22/2020 (12:30 - 2:30) 12/22/2020 (PM) 12/22/2020
Corrections:


Miscellaneous/Other
Comment Only
12/22/2020
5# east underground sanitary and flammable waste.

Plumbing Rough-in Inspection Failed 12/23/2020 (12:30 - 2:30) 12/23/2020 (PM) 12/23/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/23/2020

Miscellaneous/Other
Outstanding
03/31/2021
Nate, here is the history of the last inspection at 5601 American Blvd. on December 23, 2020 No call, no show Failed Pipe covered by dirt No air test Unable to do inspection Needs air test You will receive no inspections until this underground air test is completed. Isolate the west wing and air test underground. No connection to other underground mains. If clean out does not exist to isolate the west wing dig it up and install one. Call for inspection when completed. Inspection cancelled for 3/31/2021

Plumbing Rough-in Inspection Partial Pass 3/31/2021 (12:30 - 2:30) 3/31/2021 (PM) 03/31/2021
Corrections:


Miscellaneous/Other
Comment Only
03/31/2021
Air test on stacks on west end units

Plumbing Rough-in Inspection Partial Pass 4/1/2021 (10:00 - 12:00) 4/1/2021 (AM) 04/01/2021
Corrections:


All corrections have been made.
Comment Only
04/01/2021
Air test on one overflow rain leader and 2 storm drains. Air test on 5 units on east side

Plumbing Rough-in Inspection Partial Pass 4/5/2021 (12:30 - 2:30) 4/5/2021 (PM) 04/05/2021
Corrections:


All corrections have been made.
Comment Only
04/05/2021
Air test on one overflow rain leader and 2 storm drains. Air test on 5 units on east side 4/5/21 Walk through of 515-530 517, 518?

Plumbing Rough-in Inspection Partial Pass 4/7/2021 (12:30 - 2:30) 4/7/2021 (PM) 04/07/2021
Corrections:


Miscellaneous/Other
Comment Only
04/08/2021
4th floor walk through approved

Plumbing Rough-in Inspection Partial Pass 4/12/2021 (12:30 - 2:30) 4/12/2021 (PM) 04/12/2021
Corrections:


Miscellaneous/Other
Comment Only
04/12/2021
3rd floor walk through ok to cover

Plumbing Rough-in Inspection Partial Pass 4/14/2021 (12:30 - 2:30) 4/14/2021 (PM) 04/14/2021
Corrections:


Miscellaneous/Other
Comment Only
04/14/2021
Air test on 2 roof drains and 2 overflows

Plumbing Rough-in Inspection Partial Pass 4/21/2021 (10:00 - 12:00) 4/21/2021 (AM) 04/21/2021
Corrections:


Miscellaneous/Other
Comment Only
04/21/2021
2nd floor walk through 215-230

Plumbing Rough-in Inspection Partial Pass 4/22/2021 (12:30 - 2:30) 4/22/2021 (PM) 04/23/2021
Corrections:


Miscellaneous/Other
Comment Only
04/23/2021
1st floor walk through units 115-130

Plumbing Rough-in Inspection Partial Pass 5/24/2021 (12:30 - 2:30) 5/24/2021 (PM) 05/24/2021
Corrections:


Minimum Clearance
Comment Only
05/24/2021
Air tests on 21 stacks on west side

Plumbing Rough-in Inspection Partial Pass 5/26/2021 (12:30 - 2:30) 5/26/2021 (PM) 05/26/2021
Corrections:


Miscellaneous/Other
Comment Only
05/26/2021
5th and 4th floor walk throughs

Plumbing Rough-in Inspection Partial Pass 5/27/2021 (12:30 - 2:30) 6/1/2021 (PM) 06/01/2021
3rd floor west half of building. Passed. Partial pass for ongoing inspections. Plumbing rough in for all units. Parking ramp - west rain liter air test - 3 lb. Roof overflow drain - west exterior of building air test - 3 lb.
Plumbing Rough-in Inspection Partial Pass 6/1/2021 (12:30 - 2:30) 6/2/2021 (PM) 06/02/2021
Plumbing Rough-in Inspection Partial Pass 6/2/2021 (12:30 - 2:30) 6/2/2021 (PM) 06/02/2021
Plumbing Rough-in Inspection Partial Pass 7/7/2021 (2:30 - 3:30) 7/7/2021 (PM) 07/07/2021
Corrections:


Miscellaneous/Other
Comment Only
07/07/2021
Correction on 2nd floor stack ok Walk through garage: storm drains ok Waste and vent ok Future inspection of waters

Plumbing Rough-in Inspection Partial Pass 10/5/2021 (12:30 - 2:30) 10/5/2021 (PM) 10/05/2021
Corrections:


Miscellaneous/Other
Comment Only
10/05/2021
Began east side walk through Nate will text room numbers

Plumbing Final Inspection Partial Pass 10/6/2021 (12:30 - 2:30) 10/6/2021 (PM) 10/06/2021
Corrections:


Miscellaneous/Other
Comment Only
10/06/2021
Final walk through east side

Plumbing Rough-in Inspection Partial Pass 10/27/2021 (12:30 - 2:30) 10/27/2021 (PM) 10/27/2021
Corrections:


Miscellaneous/Other
Comment Only
10/27/2021
Manometer tests on the east side

Plumbing Rough-in Inspection Partial Pass 11/24/2021 (12:30 - 2:30) 11/24/2021 (PM) 11/24/2021
5th 4th and 3rd floor walk thru Final. Start on 5th floor.
Corrections:


Miscellaneous/Other
Comment Only
11/24/2021
final walk through of west 5,4 and 3

Plumbing Final Inspection Partial Pass 11/30/2021 (12:30 - 2:30) 11/30/2021 (PM) 11/30/2021
Corrections:


Miscellaneous/Other
Comment Only
11/30/2021
Kitchen faucet sprayers hung up in 206 and 113 Secure dishwasher in 102 Faucets in men’s and women’s locker rooms Incomplete units-missing counter tops 204 205 112 110 104

Plumbing Final Inspection Passed 12/1/2021 (12:30 - 2:30) 12/1/2021 (PM) 12/01/2021
Manometer test