PRPL202009011
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Passed | 8/20/2020 (2:30 - 3:30) | 8/20/2020 (PM) | 08/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/20/2020
Air test on waste and vent. Ok to make tie-ins
|
||||
Plumbing Final Inspection | Passed | 11/4/2020 (12:30 - 2:30) | 11/4/2020 (PM) | 11/04/2020 |
Corrections:
Minimum Clearance
Comment Only
11/04/2020
Unable to locate building permit, final is ok
|