PRPL202100364
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Final Inspection | Pending | |||
Progress Inspection | Pending | |||
Plumbing Rough-in Inspection | Partial Pass | 1/15/2021 (12:30 - 2:30) | 1/15/2021 (PM) | 01/15/2021 |
Plumbing Rough-in Inspection | Partial Pass | 1/20/2021 (2:30 - 3:30) | 1/20/2021 (PM) | 01/20/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/20/2021
Viewed 2 locations of piping that was replaced, from main line to in wall. Piping , connectors, and fittings approved. Ok to cover with soils and place concrete for slab.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 01/27/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/27/2021
3 more locations of piping replaced in 1900 Bldg. And 1 location of piping replaced in 1920 Bldg. Piping that was removed was in ground, bad piping was removed until they could connect to a good section of piping for reconnection with new fittings and piping to connect all piping together... approved
|
||||
Plumbing Rough-in Inspection | Partial Pass | 02/02/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/02/2021
Building 1920, 3 more locations of in ground piping located on hallway viewed. Piping sections that were bad, were removed to a point of good piping to connect to and replaced bad sections.... approved
|
||||
Plumbing Rough-in Inspection | Passed | 02/05/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/05/2021
Location in hallway of replaced underground plumbing piping approved. Ok to cover.
|
||||
Progress Inspection | Partial Pass | 02/10/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
Two more locations of underground piping that was replaced with new. The piping was removed to where original piping is in good condition, and new piping with the proper fittings was reinstalled to connect the system. ... approved
|