Permit Number: PRPL202110111

Plumbing
Finaled
08/19/2021
11/22/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 10/8/2021 (8:00 - 10:00) 10/8/2021 (AM) 10/08/2021
Corrections:


Miscellaneous/Other
Comment Only
10/08/2021
U.G. Air test on C.O. where it leaves the building to approx. 40’ of sanitary main

Plumbing Rough-in Inspection Partial Pass 10/12/2021 (10:00 - 12:00) 10/12/2021 (AM) 10/12/2021
Corrections:


Miscellaneous/Other
Comment Only
10/12/2021
AirTest on under ground main and piping to 2-2” floor drains

Plumbing Rough-in Inspection Partial Pass 10/15/2021 (10:00 - 12:00) 10/15/2021 (AM) 10/15/2021
Corrections:


Miscellaneous/Other
Comment Only
10/15/2021
Air test on under ground sanitary

Plumbing Rough-in Inspection Partial Pass 10/19/2021 (8:00 - 10:00) 10/19/2021 (AM) 10/19/2021
Corrections:


Miscellaneous/Other
Comment Only
10/19/2021
Air test on under ground sanitary. North east

Plumbing Rough-in Inspection Partial Pass 10/22/2021 (8:00 - 10:00) 10/22/2021 (AM) 10/22/2021
Corrections:


Miscellaneous/Other
Comment Only
10/22/2021
Air test on sink by the tank. Visual on under ground storm drain on north side

Plumbing Rough-in Inspection Partial Pass 10/26/2021 (8:00 - 10:00) 10/26/2021 (AM) 10/26/2021
Corrections:


Miscellaneous/Other
Comment Only
10/26/2021
Air test on under ground sanitary main west end

Plumbing Rough-in Inspection Partial Pass 11/1/2021 (10:00 - 12:00) 11/1/2021 (AM) 11/01/2021
Corrections:


Miscellaneous/Other
Comment Only
11/01/2021
Air test on back to back bathrooms Visual on 18” storm drain, ok to cover as needed

Plumbing Rough-in Inspection Partial Pass 11/2/2021 (10:00 - 12:00) 11/2/2021 (AM) 11/02/2021
Corrections:


Miscellaneous/Other
Comment Only
11/02/2021
Rain leader underground, section of piping at north center of building. Air test holding at 3psi. Approved to cover.

Plumbing Rough-in Inspection Partial Pass 11/3/2021 (10:00 - 12:00) 11/3/2021 (AM) 11/03/2021
Corrections:


Miscellaneous/Other
Comment Only
11/03/2021
Air test on 18” under ground storm

Plumbing Rough-in Inspection Partial Pass 11/8/2021 (8:00 - 10:00) 11/8/2021 (AM) 11/08/2021
Corrections:


Minimum Clearance
Comment Only
11/08/2021
Air test on 12” and 18”

Minimum Clearance
Comment Only
11/08/2021
Air test on 12” and 18” storm drain

Plumbing Rough-in Inspection Partial Pass 11/10/2021 (8:00 - 10:00) 11/10/2021 (AM) 11/10/2021
Corrections:


Minimum Clearance
Comment Only
11/10/2021
Air test on remainder of storm pipe. Cover everything necessary for rain.

Plumbing Rough-in Inspection Partial Pass 11/12/2021 (8:00 - 10:00) 11/12/2021 (AM) 11/12/2021
Corrections:


Miscellaneous/Other
Comment Only
11/12/2021
Air test on waste for 2 floor drains

Plumbing Rough-in Inspection Partial Pass 11/16/2021 (8:00 - 10:00) 11/16/2021 (AM) 11/16/2021
Corrections:


Minimum Clearance
Comment Only
11/16/2021
Under ground Air test on trench drain, 2 floor drains and a mop sink Under ground completed

Plumbing Rough-in Inspection Partial Pass 12/16/2021 (8:00 - 10:00) 12/16/2021 (AM) 12/16/2021
Corrections:


Miscellaneous/Other
Comment Only
12/16/2021
South bathroom group water piping, drain and venting. Air test holding at 5psi. … approved

Plumbing Rough-in Inspection Partial Pass 12/30/2021 (10:00 - 12:00) 12/30/2021 (AM) 12/30/2021
Corrections:


Miscellaneous/Other
Comment Only
12/30/2021
Visual on primary roof drains. Future 3 pound air tests

Plumbing Rough-in Inspection Partial Pass 1/4/2022 (8:00 - 10:00) 1/4/2022 (AM) 01/04/2022
Corrections:


Miscellaneous/Other
Comment Only
01/04/2022
Visual and 5 lb. air test on bathroom groups on 1st floor

Plumbing Rough-in Inspection Partial Pass 1/11/2022 (8:00 - 10:00) 1/11/2022 (AM) 01/11/2022
Visually inspected water lines for bathrooms and kitchen area.
Plumbing Rough-in Inspection Partial Pass 1/28/2022 (10:00 - 12:00) 1/28/2022 (AM) 01/28/2022
Rain water inspections complete.
Plumbing Rough-in Inspection Partial Pass 2/10/2022 (8:00 - 10:00) 2/10/2022 (AM) 02/10/2022
5 lb. Air test on bathroom group on west side of dock doors, and visual on drains on roofs for entrances.
Plumbing Rough-in Inspection Passed 2/15/2022 (8:00 - 10:00) 2/15/2022 (AM) 02/15/2022
Shower pan inspection good.
Plumbing Final Inspection Partial Pass 03/24/2022
Corrections:


Miscellaneous/Other
Comment Only
03/24/2022
Progress inspection.

Plumbing Rough-in Inspection Passed 4/6/2022 (10:00 - 12:00) 4/6/2022 (AM) 04/06/2022
Plumbing Final Inspection Partial Pass 04/06/2022
Corrections:


Miscellaneous/Other
Comment Only
04/06/2022
Manometer tests okay. Reschedule for final inspection.

Plumbing Final Inspection Passed 5/26/2022 (8:00 - 10:00) 5/26/2022 (AM) 05/26/2022