PRPL202110565
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Partial Pass | 9/22/2021 (8:00 - 10:00) | 9/22/2021 (AM) | 09/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2021
Informational inspection with Sam.
Superintendent would appreciate a construction meeting. Rebecca will discuss with Duke and respond to them.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/25/2021 (8:00 - 10:00) | 10/25/2021 (AM) | 10/25/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2021
Air test on all rain leaders
Visual on rough floors 2-5
Increase rod size on 6”rain leaders rods from 3/8” - 1/2”
|
||||
Plumbing Rough-in Inspection | Partial Pass | 12/27/2021 (10:00 - 12:00) | 12/27/2021 (AM) | 12/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/27/2021
Consultation with Ryan about elevator sump drains. Increase drain size from 2”.
Follow approved plan.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/11/2022 (10:00 - 12:00) | 1/11/2022 (AM) | 01/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/11/2022
Fix back pitched kitchen waste line, and add straps for water supply lines within stud spaces
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/12/2022 (8:00 - 10:00) | 1/12/2022 (AM) | 01/12/2022 |
Signed off 4th floor, signed off north side 3rd floor. Discussed finishing insulation on 3rd floor recirc line, and elevator drains. Requiring 4” drains on elevator pits. | ||||
Plumbing Rough-in Inspection | Partial Pass | 1/13/2022 (2:30 - 3:30) | 1/13/2022 (PM) | 01/13/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/13/2022
Visually inspected dwv piping 3rd floor
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/18/2022 (8:00 - 10:00) | 1/18/2022 (AM) | 01/18/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/18/2022
5 lb Air test 2nd-4th, visually inspect 2nd and 3rd rough in
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/19/2022 (10:00 - 12:00) | 1/19/2022 (AM) | 01/19/2022 |
Plumbing Rough-in Inspection | Partial Pass | 1/20/2022 (10:00 - 12:00) | 1/20/2022 (AM) | 01/20/2022 |
Plumbing Rough-in Inspection | Partial Pass | 1/28/2022 (8:00 - 10:00) | 1/28/2022 (AM) | 01/28/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
01/28/2022
5 lb. Air test on northeast section of underground.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/31/2022 (8:00 - 10:00) | 1/31/2022 (AM) | 01/31/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2022
5 lb. Air test on northeast section of underground.
|
||||
Miscellaneous/Other
Comment Only
01/31/2022
5 lb. Air test on northwest section of underground
|
||||
Plumbing Rough-in Inspection | Partial Pass | 2/3/2022 (8:00 - 10:00) | 2/3/2022 (AM) | 02/03/2022 |
Spoke about elevator sump basket waste line | ||||
Plumbing Rough-in Inspection | Partial Pass | 2/7/2022 (8:00 - 10:00) | 2/7/2022 (AM) | 02/07/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/07/2022
Discussed pumping elevator pit waste from sump to 4” stand pipe in dead space, and venting the stand pipe to meet code requirements.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 2/10/2022 (10:00 - 12:00) | 2/10/2022 (AM) | 02/10/2022 |
Elevator pit drain to basket piping on North elevator good. Ok to backfill. | ||||
Plumbing Rough-in Inspection | Partial Pass | 2/17/2022 (8:00 - 10:00) | 2/17/2022 (AM) | 02/17/2022 |
Inspected 2- 4” elevator pit drains and piping on south elevator shaft. Discussed bar area on first floor. | ||||
Plumbing Rough-in Inspection | Partial Pass | 2/24/2022 (10:00 - 12:00) | 2/24/2022 (AM) | 02/24/2022 |
5 lb. Air test on bar underground, okay to cover. 5 lb. Air test on grease waste line. Okay to cover. | ||||
Plumbing Rough-in Inspection | Partial Pass | 3/22/2022 (12:30 - 2:30) | 03/22/2022 | |
Progress inspection. | ||||
Plumbing Rough-in Inspection | Partial Pass | 5/10/2022 (10:00 - 12:00) | 5/10/2022 (AM) | 05/10/2022 |
Units 100-115, Air test, and visual. Rough in’s okay. | ||||
Plumbing Rough-in Inspection | Partial Pass | 5/17/2022 (12:30 - 2:30) | 5/17/2022 (PM) | 05/17/2022 |
Visual on remaining 1st floor rooms. Will give air test with horizontal waste piping in garage when ready. Will schedule another rough in inspection when finished dropping waste/vent piping through floor. | ||||
Rough In Inspection | Partial Pass | 07/28/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/28/2022
Air test on gas piping splitting off up to roof and lower level okay. No visual on piping above 1st floor. City of Bloomington not liable for visual inspection as piping is covered. Visual on rough plumbing for commercial kitchen area. No air test on dwv piping for kitchen yet.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 8/29/2022 (10:00 - 12:00) | 8/29/2022 (AM) | 08/29/2022 |
Corrections:
Miscellaneous/Other
Comment Only
08/29/2022
Visual and 5 lb. Air test on new underground waste piping draining into sump baskets in lower lever. May proceed and cover.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 9/22/2022 (12:30 - 2:30) | 9/22/2022 (PM) | 09/22/2022 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2022
Inspection of underground waste piping serving floor drains in pool area.
|
||||
Plumbing Rough-in Inspection | Not Ready | 10/20/2022 (12:30 - 2:30) | 10/20/2022 (PM) | 10/20/2022 |
Corrections:
Miscellaneous/Other
Comment Only
10/20/2022
Inspection was for gas piping from a different permit.
|
||||
Rough In Inspection | Partial Pass | 12/13/2022 (10:00 - 12:00) | 12/13/2022 (AM) | 12/13/2022 |
Corrections:
Miscellaneous/Other
Comment Only
12/13/2022
Air tests okay all remaining rough waste piping.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 1/24/2023 (8:00 - 10:00) | 1/24/2023 (AM) | 01/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/24/2023
Visual and air test on portion of aboveground waste and vent piping in lower level.
|
||||
Rough In Inspection | Partial Pass | 1/25/2023 (8:00 - 10:00) | 1/25/2023 (AM) | 01/25/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/25/2023
Visual and air test on remaining in wall dwv in lower level. May proceed and cover.
|
||||
Plumbing Rough-in Inspection | Passed | 1/30/2023 (8:00 - 10:00) | 1/30/2023 (AM) | 01/30/2023 |
Corrections:
Miscellaneous/Other
Comment Only
01/30/2023
Air test on gas line in lower level. Finish strapping water lines in wall cavities.
|
||||
Rough In Inspection | Passed | 2/3/2023 (8:00 - 10:00) | 2/3/2023 (AM) | 02/03/2023 |
Corrections:
Miscellaneous/Other
Comment Only
02/03/2023
Vent connections for bar area okay. May proceed and cover.
|
||||
Plumbing Final Inspection | Partial Pass | 3/23/2023 (8:00 - 10:00) | 3/23/2023 (AM) | 03/23/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/23/2023
Manometer tests okay on the first two of the four potential manometer tests.
|
||||
Plumbing Final Inspection | Partial Pass | 3/24/2023 (8:00 - 10:00) | 3/24/2023 (AM) | 03/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
03/24/2023
Manometer tests on remaining units okay. Still need manometer on lower level.
|
||||
Plumbing Final Inspection | Partial Pass | 4/20/2023 (8:00 - 10:00) | 4/20/2023 (AM) | 04/20/2023 |
Plumbing Final Inspection | Partial Pass | 4/24/2023 (12:30 - 2:30) | 4/24/2023 (PM) | 04/24/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/24/2023
Final visual inspection on 4th floor okay for all units except 434 and for the icemaker. Finish caulking fixtures that were on list sent to Ryan.
|
||||
Plumbing Final Inspection | Partial Pass | 4/26/2023 (8:00 - 10:00) | 4/26/2023 (AM) | 04/26/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/26/2023
Final visual inspection of all units on 3 rd floor except the 34 unit okay.
|
||||
Plumbing Final Inspection | Partial Pass | 4/27/2023 (10:00 - 12:00) | 4/27/2023 (AM) | 04/27/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2023
Final visual inspection okay for all units on 2nd floor except for 248 and 250.
|
||||
Plumbing Final Inspection | Partial Pass | 4/28/2023 (8:00 - 10:00) | 4/28/2023 (AM) | 04/28/2023 |
Corrections:
Miscellaneous/Other
Comment Only
04/28/2023
Visual inspection okay on units on 1st floor except the list sent to the foreman Ryan.
|
||||
Plumbing Final Inspection | Partial Pass | 5/26/2023 (Afternoon) | 5/26/2023 (PM) | 05/26/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/26/2023
Manometer tests on lower level okay. Visual inspection of portion of lower level okay.
|
||||
Plumbing Final Inspection | Partial Pass | 5/30/2023 (8:00 - 10:00) | 5/30/2023 (AM) | 05/30/2023 |
Corrections:
Miscellaneous/Other
Comment Only
05/30/2023
Add backflow prevention to all ice makers.
|
||||
Plumbing Final Inspection | Partial Pass | 5/31/2023 (12:30 - 2:30) | 5/31/2023 (PM) | 05/31/2023 |
Plumbing Final Inspection | Not Ready | 6/16/2023 (12:30 - 2:30) | 6/16/2023 (PM) | 06/16/2023 |
Plumbing Final Inspection | Partial Pass | 6/23/2023 (8:00 - 10:00) | 6/23/2023 (AM) | 06/23/2023 |
Plumbing Final Inspection | Not Ready | 6/26/2023 (8:00 - 10:00) | 6/26/2023 (AM) | 06/26/2023 |
Plumbing Rough-in Inspection | Passed | 6/30/2023 (8:00 - 10:00) | 6/30/2023 (AM) | 06/30/2023 |
Corrections:
Miscellaneous/Other
Comment Only
06/30/2023
Shower pan inspections okay for units 238 and 338.
|
||||
Plumbing Rough-in Inspection | Passed | 7/3/2023 (8:00 - 10:00) | 7/3/2023 (AM) | 07/03/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/03/2023
Shower pan inspection okay for 438.
|
||||
Plumbing Final Inspection | Partial Pass | 7/12/2023 (12:30 - 2:30) | 7/12/2023 (PM) | 07/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2023
Install pump and piping for sump basket for drain tile in mechanical room and pipe to storm sewer piping. Also permanently cap abandoned pvc piping next sump basket.
|
||||
Plumbing Final Inspection | Passed | 7/17/2023 (12:30 - 2:30) | 7/17/2023 (PM) | 07/17/2023 |