PRPL202114911
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Rough-in Inspection | Failed | 10/20/2022 | ||
Corrections:
Miscellaneous/Other
Carried Forward
10/20/2022
Contractor provided air test on gas piping from main to roof, to generator pad, and outlet for fire pit on patio. No visual on underground piping for generator. Need to expose portions of piping to ensure proper burial depth. Contractor is aware about needing to change the underground csst piping under the concrete in the patio area. Need to add supports for csst running through 1st floor ceiling.
|
||||
Plumbing Rough-in Inspection | Partial Pass | 10/25/2022 (8:00 - 10:00) | 10/25/2022 (AM) | 10/25/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
10/25/2022
Contractor provided air test on gas piping from main to roof, to generator pad, and outlet for fire pit on patio. No visual on underground piping for generator. Need to expose portions of piping to ensure proper burial depth. Contractor is aware about needing to change the underground csst piping under the concrete in the patio area. Need to add supports for csst running through 1st floor ceiling.
|
||||
Miscellaneous/Other
Comment Only
10/25/2022
Gas line to shallow under sidewalk to generator cannot use patio gas line covered in concrete was not seen pressure test on
|
||||
Plumbing Rough-in Inspection | Passed | 07/12/2023 | ||
Corrections:
Miscellaneous/Other
Outstanding
10/25/2022
Contractor provided air test on gas piping from main to roof, to generator pad, and outlet for fire pit on patio. No visual on underground piping for generator. Need to expose portions of piping to ensure proper burial depth. Contractor is aware about needing to change the underground csst piping under the concrete in the patio area. Need to add supports for csst running through 1st floor ceiling.
|
||||
Plumbing Final Inspection | Passed | 07/12/2023 |