PRPL202114912
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Plumbing Final Inspection | Partial Pass | 11/15/2021 (8:00 - 10:00) | 11/15/2021 (AM) | 11/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/15/2021
Heaters fired up Monday morning. Left off over the weekend. Plumber found many leaks on initial pressure test. Leaks repaired.
|
||||
Plumbing Final Inspection | Partial Pass | 12/3/2021 (10:00 - 12:00) | 12/3/2021 (AM) | 12/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/03/2021
Walk through upper floors
Still 1st floor to do
|
||||
Plumbing Final Inspection | Partial Pass | 1/10/2022 (8:00 - 10:00) | 1/10/2022 (AM) | 01/10/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2022
5 lb air test 2nd-4th east units, discussed elevator pit drains
|
||||
Plumbing Rough-in Inspection | Partial Pass | 07/18/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
07/18/2022
Progress inspection. Shower bases set, continuing work on water main, still continuing work on lower level.
|
||||
Plumbing Rough-in Inspection | Passed | 11/01/2023 | ||
Plumbing Final Inspection | Passed | 11/01/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/01/2023
Construction complete. Need for temporary heat done.
|