Summary

PRPL202116148
Plumbing
Finaled
BLOOMINGTON HOTEL VENTURE
Alteration/Repair/Replace
Install 216 sinks and 21 washer boxes on existing locations. same as model unit previously applied for
12/09/2021
12/17/2021
10/16/2023
04/19/2023

Locations

Permits

Permit Number: PRPL202116148

Plumbing
Finaled
12/17/2021
10/16/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Plumbing Rough-in Inspection Partial Pass 1/10/2022 (10:00 - 12:00) 1/10/2022 (AM) 01/10/2022
Brace water lines, protect copper from dissimilar metals, run kitchen wastes in 2” pipe
Plumbing Rough-in Inspection Partial Pass 1/13/2022 (12:30 - 2:30) 1/13/2022 (PM) 01/13/2022
Corrections:


Miscellaneous/Other
Comment Only
01/13/2022
Finish securing kitchen water lines on 8th floor. 8th floor rough in okay.

Plumbing Rough-in Inspection Partial Pass 1/24/2022 (12:30 - 2:30) 1/24/2022 (PM) 01/24/2022
Corrections:


Miscellaneous/Other
Comment Only
01/24/2022
Visually inspected units on 9th floor for rough in. 9th floor units ok. No laundries inspected on 8th or 9th yet,

Plumbing Rough-in Inspection Partial Pass 2/15/2022 (12:30 - 2:30) 2/15/2022 (PM) 02/15/2022
Visual on 10th floor dwv, will see remainder of 10th when scheduled for 11th
Plumbing Rough-in Inspection Partial Pass 3/1/2022 (10:00 - 12:00) 3/1/2022 (AM) 03/01/2022
Corrections:


Miscellaneous/Other
Carried Forward
03/01/2022
11th floor walk through Room #1136 Change fernco to mission coupling Room 912 fire caulk closet bend in ceiling

Plumbing Rough-in Inspection Partial Pass 3/22/2022 (2:30 - 3:30) 3/22/2022 (PM) 03/22/2022
Corrections:


Miscellaneous/Other
Resolved
03/22/2022
11th floor walk through Room #1136 Change fernco to mission coupling Room 912 fire caulk closet bend in ceiling

Miscellaneous/Other
Carried Forward
03/22/2022
Change tailpiece length on washer boxes on 8th and 9th floor and submit a picture to me showing the correction.

Plumbing Rough-in Inspection Partial Pass 4/15/2022 (8:00 - 10:00) 03/30/2022
Corrections:


Miscellaneous/Other
Resolved
03/30/2022
Change tailpiece length on washer boxes on 8th and 9th floor and submit a picture to me showing the correction.

Miscellaneous/Other
Comment Only
03/30/2022
Inspection of rough-in plumbing on laundry rooms on 10th-14th floors. Okay to cover.

Plumbing Final Inspection Not Ready 3/30/2022 (8:00 - 10:00) 3/30/2022 (AM) 03/30/2022
Corrections:


Miscellaneous/Other
Carried Forward
03/30/2022
Final inspection for portion of units on 8th floor. Need to finish connecting and securing dishwashers, and add hammer arrestors to water supply lines to dishwashers.

Plumbing Final Inspection Partial Pass 3/31/2022 (10:00 - 12:00) 3/31/2022 (AM) 03/31/2022
Corrections:


Miscellaneous/Other
Comment Only
03/31/2022
Final inspection for portion of units on 8th floor. Plumbing final inspection ok for units 801,803,804,806,808,810,813,814,818, 819, and 829. Permit still open.

Plumbing Rough-in Inspection Partial Pass 4/15/2022 (8:00 - 10:00) 4/15/2022 (AM) 04/15/2022
Corrections:


Miscellaneous/Other
Outstanding
04/15/2022
Visual rough in inspection all 12th floor units, except the 3 units on the east end corridor. Change out all ferncos and make corrections on backpitched pipe.

Plumbing Final Inspection Partial Pass 04/15/2022
Corrections:


Miscellaneous/Other
Comment Only
04/15/2022
Final inspection on 806, 808, 814, 828, 830, and 833 okay.

Plumbing Rough-in Inspection Not Ready 4/20/2022 (12:30 - 2:30) 4/20/2022 (PM) 04/20/2022
Plumbing Final Inspection Partial Pass 4/27/2022 (10:00 - 12:00) 4/27/2022 (AM) 04/27/2022
Final inspection okay for units 832,834,835,836, and 843.
Plumbing Rough-in Inspection Partial Pass 5/2/2022 (10:00 - 12:00) 5/2/2022 (AM) 05/02/2022
Rough in’s okay on 12th floor. All Fernco’s will be eliminated.
Plumbing Final Inspection Partial Pass 5/12/2022 (8:00 - 10:00) 5/12/2022 (AM) 05/12/2022
Final on units 908,910,920,921,922,923,924,928,929, 934, and 941. Rough in on units 1419,1420,1422,1423,1424,1425,1429, 1430,1431,1434-36.
Plumbing Final Inspection Partial Pass 5/19/2022 (10:00 - 12:00) 5/19/2022 (AM) 05/19/2022
Corrections:


Miscellaneous/Other
Comment Only
05/19/2022
9th fl final walk through. Set 3 sinks and secure one dishwasher.

Plumbing Final Inspection Partial Pass 6/10/2022 (8:00 - 10:00) 6/10/2022 (AM) 06/10/2022
Inspection cancelled for 6/8/22 by steinkraus. jms 6/7/22
Corrections:


Miscellaneous/Other
Comment Only
06/10/2022
Final on1001,1014,1024,1030,1033,1034,10371028, and 1042. Laundry rough in on 3rd floor okay.

Plumbing Final Inspection Partial Pass 7/15/2022 (10:00 - 12:00) 06/21/2022
Corrections:


Miscellaneous/Other
Comment Only
06/21/2022
Final on units 1004, 1014, 1032,1035, and 1039.

Plumbing Final Inspection Partial Pass 6/23/2022 (12:30 - 2:30) 6/23/2022 (PM) 06/23/2022
Corrections:


Miscellaneous/Other
Comment Only
06/23/2022
Rough in inspection on 14th floor. Still need inspection for 1407, 1421, and 1432 and work by pool.

Plumbing Rough-in Inspection Partial Pass 6/24/2022 (12:30 - 2:30) 6/24/2022 (PM) 06/24/2022
Corrections:


Miscellaneous/Other
Carried Forward
06/24/2022
Finals for all units on 10th okay, except units 07,10,16,18,20,21,22,23,24,26,and 40

Plumbing Final Inspection Partial Pass 7/13/2022 (8:00 - 10:00) 7/13/2022 (AM) 07/13/2022
Corrections:


Miscellaneous/Other
Comment Only
07/13/2022
Final inspection on units on 11th floor okay, except for the following which are not complete: 1117,1135,1120,1134,1133,1121,1132,1122,1123,1130,1124,1126,1127,and 1129.

Plumbing Final Inspection Partial Pass 7/15/2022 (10:00 - 12:00) 7/15/2022 (AM) 07/15/2022
Corrections:


Miscellaneous/Other
Comment Only
07/15/2022
Final for units 1109,1136,1135,1134,1133,1132,1131, 1129,1127, and 1126.

Plumbing Rough-in Inspection Partial Pass 7/22/2022 (8:00 - 10:00) 7/22/2022 (AM) 07/22/2022
Rough in for bathroom by pool okay, final on laundry on 11th okay.
Corrections:


Miscellaneous/Other
Carried Forward
07/22/2022
Finals for all units on 10th okay, except units 07,10,16,18,20,21,22,23,24,26,and 40.

Plumbing Final Inspection Partial Pass 07/25/2022
Corrections:


Miscellaneous/Other
Comment Only
07/25/2022
Final on units 1120 and 1130 okay.

Plumbing Final Inspection Partial Pass 8/4/2022 (10:00 - 12:00) 8/4/2022 (AM) 08/04/2022
Corrections:


Miscellaneous/Other
Comment Only
08/04/2022
1/2 of 12th floor finalled Replace one fernco and add hanger

Plumbing Final Inspection Partial Pass 8/12/2022 (10:00 - 12:00) 8/12/2022 (AM) 08/12/2022
Corrections:


Miscellaneous/Other
Comment Only
08/12/2022
12th floor finals One dishwasher to remount

Plumbing Rough-in Inspection Partial Pass 9/20/2022 (12:30 - 2:30) 9/20/2022 (PM) 09/21/2022
Rouen in okay for pool area bathroom.
Corrections:


Miscellaneous/Other
Carried Forward
09/21/2022
Finals for all units on 10th okay, except units 07,10,16,18,20,21,22,23,24,26,and 40.

Plumbing Final Inspection Partial Pass 10/28/2022 (12:30 - 2:30) 10/28/2022 (PM) 10/28/2022
Corrections:


Miscellaneous/Other
Comment Only
10/28/2022
Secure dishwashers in 13 & 14 Laundry ok Walk through of 20 rooms on 14th floor

Plumbing Rough-in Inspection Partial Pass 11/8/2022 (10:00 - 12:00) 11/8/2022 (AM) 11/08/2022
Corrections:


Miscellaneous/Other
Resolved
11/08/2022

Miscellaneous/Other
Comment Only
11/08/2022
Visual inspection on piping to sump basket for drain in lift in pool area. Also visual inspection of units on 14th floor. Still need finals on 1421,23,24,and 32.

Plumbing Final Inspection Partial Pass 1/26/2023 (8:00 - 10:00) 1/26/2023 (AM) 01/26/2023
Corrections:


Miscellaneous/Other
Comment Only
01/26/2023
Visual final on remaining units on 8th and 9th okay.

Plumbing Final Inspection Partial Pass 2/16/2023 (8:00 - 10:00) 2/16/2023 (AM) 02/16/2023
Corrections:


Miscellaneous/Other
Comment Only
02/16/2023
Remove boiler drain from lav water line in pool bathroom.

Plumbing Final Inspection Partial Pass 3/8/2023 (12:30 - 2:30) 3/8/2023 (PM) 03/08/2023
Corrections:


Miscellaneous/Other
Comment Only
03/08/2023
Finish securing dishwashers, setting toilets, installing tub trims, and dapping. Call for reinspection when ready.

Plumbing Final Inspection Passed 4/19/2023 (7:00 - 8:00) 4/19/2023 (AM) 04/19/2023
Corrections:


Miscellaneous/Other
Comment Only
04/19/2023
Dishwashers in 1021,1220, and 1224 still need to be secured. Bracket not installed yet. Building inspector will verify on building final. Final visual inspection okay.